Call for tenders' details

Title:
Implementation of 2020 EU biodiversity strategy: priorities for the restoration ...
Contracting authority:
European Commission, DG ENV+CLIMA
TED publication date:
01/06/2012
Time limit for receipt of tenders:
16/07/2012
Status:
Closed
Show filter parameters

Results per page: 10 | 25 | 50 10 Questions found, displaying all Questions .
# Question Answer Last publication date Status
10
Under 5.Deliverables the ToR specify the timing of the different steps. Is it possible to propose an [...]
1) It is possible to propose an alternative time schedule along with an accompanying justification. 2 [...]
06/07/2012
9
Depending on the type of ecosystems at stake, there may be many government services involved. How should [...]
The Commission will guide the contractor with regard to the appropriate contact points in the Member [...]
18/06/2012
8
MS should be invited to the workshops. How to deal with different viewpoints and governmental levels [...]
The participation to the workshops will be finalised as part of the relevant task, after consultation [...]
18/06/2012
7
Should support mechanisms be at global, EU, national or sub-national scale or all? What should be the [...]
The intention is to explore the nature and potential benefits of such a facility. This would include [...]
18/06/2012
6
Investments by private parties are voluntary. They have their own priorities. The framework should allow [...]
The strategic framework is intended as a tool to guide decision makers towards the most efficient options [...]
18/06/2012
5
Task 1B: The last option mentioned reads '.....on the lowest net cost to the EU.....'. Do you mean the [...]
The EU as the assembly of all Member States. The second part of the question is left to the appreciation [...]
18/06/2012
4
Criteria for priority setting are political and will differ between MS and in time. Within a MS different [...]
The achievement of target 2 will be a contribution to the attainment of the overall policy objectives [...]
18/06/2012
3
Will the development of a strategic framework by Member States be compulsory or voluntary, and how flexible [...]
The purpose of the contract is to support the Commission in developing a strategic framework for setting [...]
18/06/2012
2
Should the framework be applicable to terrestrial ecosystems, fresh water ecosystems, coastal zones, [...]
The framework should be applicable to all ecosystems.
18/06/2012
1
When do you expect that the contract will be signed and the project has to start?
We would expect that signature and therefore the formal start of the contract will take place between [...]
14/06/2012