Call for tenders' details

Title:
Development and maintenance of the information system of the EU emission trading...
Contracting authority:
European Commission, DG ENV+CLIMA
TED publication date:
06/04/2012
Time limit for receipt of tenders:
21/05/2012
Status:
Closed
Show filter parameters

Results per page: 10 | 25 | 50 13 Questions found, displaying 1 to 10.[First/Prev] 1, 2 [Next/Last]
# Question Answer Last publication date Status
13
From the requirements of Annex 10 of the Tender Specifications, our questions are subject to multiple [...]
The Helpdesk service to be provided under this Contract must comply with the requirements of Part 1, [...]
07/05/2012
12
Page 24 indicates the min number of experts per profile required for this project. Do you confirm that [...]
Yes.
07/05/2012
11
Do tenderers need to provide client certificates for each and every project presented in the list of [...]
The Tenderer may provide references to as many projects as he considers necessary. The Tenderer must [...]
07/05/2012
10
Clarification 1 We understand that an electronic copy of the offer is not required for submission. Could [...]
Answer Clarification 1: No electronic copy is required, but the tenderers may provide it. Answer Clarification [...]
07/05/2012
9
Clarification 1: In the tender specifications, Part 1, chapter 3.4, p. 18, it is specified that “Monitoring [...]
Clarification 1: Yes. Clarification 2: The tenderer must submit a technical offer as per point 6.3. of [...]
07/05/2012
8
Tender specifications section 3.1 p.13 “the contractor must provide the Commission with an emergency [...]
The tenderer must comply with point 3.1. of Part 1 of the Tender Specifications. Since the required helpdesk [...]
07/05/2012
7
Tender specifications section 3.1 p.13 "The helpdesk service may be asked to assist in the resolution [...]
The Help-desk service to be provided under this Contract must comply with the requirements of Part 1, [...]
04/05/2012
6
In the tender specifications p.43, we are required to provide the CV in the Europass format. Our CVs [...]
The tenderers must comply with the requirements of Part 3, point 6.2 the Tender Specifications.
04/05/2012
5
Annex 10: Service Level Guarantee “The Commission may require the Contractor's staff to work inside and [...]
In case the Commission requires the Contractor's staff to work outside of normal woking hours, the Contractor [...]
04/05/2012
4
Can you please provide us with the excel table of Annex 6? The hyperlink in the specifications does not [...]
We have uploaded a new Annex 6 Table in XL.
02/05/2012