33
|
Please kindly clarify whether for submission by private courier services, i.e. DHL or similar, only the [...]
|
Both should be mentioned as under point a) is mentioned the service in charge of the call and under point [...]
|
28/07/2011
|
|
32
|
If the European office of an international entity applies, but some of those who would be involved in [...]
|
The legal entity file of the applicant will serve to check the eligibility of "the organisation". If [...]
|
28/07/2011
|
|
31
|
please specify whether if the subcontractor is a natural person with a very small amount (for example [...]
|
Yes, no distinction is made between subcontractors, so please refer to the last page of the specifications [...]
|
27/07/2011
|
|
30
|
For Task 2, it is stated that Meetings 2 & 3 with the Commission will be on the occasion of the introductory [...]
|
In the description of task 2 it is stated under "meetings with the Commission" (see page 4) that there [...]
|
27/07/2011
|
|
29
|
Regarding the overall turnover and turnover statement..., what do the tender refer to with "concerning [...]
|
Yes, indeed : overall turnover + turnover in activities similar to the ones of the tender.
|
26/07/2011
|
|
28
|
For the evidence of Technical and professional experience, we have drafted all CV’s in our own format [...]
|
As long as all the information provided is minimum the same as in the Europass format, we can accept [...]
|
26/07/2011
|
|
27
|
The call mentions the fact that the contractor must print 300 copies of each guide (10-20 pages each) [...]
|
I should be a separate line in the budget as it are not HR costs! You can proceed as follows : under [...]
|
26/07/2011
|
|
26
|
What do the tender specifications refer to talking about "how do you intend to build on and link with [...]
|
This is standard information on which aspects to consider in general when preparing a tender. It therefore [...]
|
26/07/2011
|
|
25
|
Article 39, paragraph 2, of Directive 2004/18/EC states that additional information relating to the specifications [...]
|
The Financial Regulation (FR) and its implementing rules (IR), setting out the rules for the establishment [...]
|
25/07/2011
|
|
24
|
Section 4.2 Structure of the Tender specifies that tenders must contain continuous page numbering. However [...]
|
Of course it can be done by hand at the very end when the tender is completed. It will be very much appreciated [...]
|
25/07/2011
|
|