Call for tenders' details

Title:
ENTR/G2 - preparatory action for the recycling of mixed plastics waste.
Contracting authority:
European Commission, DG for Internal Market, Industry,Entrepreneurshipand SMEs (...
TED publication date:
04/04/2012
Time limit for receipt of tenders:
25/05/2012
Status:
Closed
Show filter parameters

Results per page: 10 | 25 | 50 26 Questions found, displaying 1 to 10.[First/Prev] 1, 2, 3 [Next/Last]
# Question Answer Last publication date Status
26
Can you confirm that tenders have to be received by your offices by 16.00 hrs on Friday 25 May - our [...]
As stated in the invitation to tender letter, the deadline for submission of tenders is 25/5/2012 (23 [...]
24/05/2012
25
Is there a form for a "statement confirming the validity of the tender?" What is meant by "preferably [...]
There is no standard form for the statement confirming the validity of the tender. You should state in [...]
22/05/2012
24
Is it meant to indicate the turnover of similar projects in the last three years?
Section 5 states that a statement of the tenderer’s general turnover for the last 3 years (yearly level [...]
22/05/2012
23
May signed documents be attached as a copy/scan? The Power of Attorney needs signatures from parties [...]
A copy/scan of the Power of Attorney document is acceptable at this stage of the tender submission. Originals [...]
22/05/2012
22
Concerning the various documents that need be delivered such as the Exclusion Criteria Form, may they [...]
At this stage of the tender procedure exclusion criteria documents can be signed with an electronic signature [...]
22/05/2012
21
Dear Madams/Sirs please let us know if for subcontractors scanned document (letter of intent, legal entity [...]
A copy/scan of the mentioned documents is acceptable at this stage of the tender submission. Originals [...]
22/05/2012
20
We understand the results of the project will be presented to a steering group and a conference as part [...]
Rights relating to intellectual property developed during the engineering phase of the demonstration [...]
16/05/2012
19
In section 1.2.4 of the tender it is stated that the costs for materials and equipment needed to assemble [...]
Materials and equipment are to be funded by the contractor (or whichever other party is prepared to provide [...]
16/05/2012
18
It is stated as part of the Deliverables section of the tender that it is expected that the engineering [...]
Tenderers may propose an alternative timetable, if what they propose covers all the elements of the project [...]
16/05/2012
17
Considering that the contractor builds a demonstration plant using a component which he bought from a [...]
The Commission acquires everything that is produced during the contract, but no pre-existing rights ( [...]
16/05/2012