14
|
Just a clarification regarding question 2 and the breakdown of costs. Can we provide in the technical [...]
|
Section III.5.2.1 of the Technical Specifications specifies that “The technical offer must not include [...]
|
09/01/2023
|
|
13
|
Could you confirm if for the evidence of T2 we need to provide both Appendix I.N and the Europass CVs [...]
|
Tenderers are encouraged to prepare both formats. However, kindly note information mentioned on page [...]
|
05/01/2023
|
|
12
|
In the document 'EN-Appendix I.A - Terms of Reference' the list of contents mentions 2 chapters: 2.3 [...]
|
Please note that the specific requirements on Environmental and social aspects and Experts profile/staff [...]
|
05/01/2023
|
|
11
|
1. Point G) of the technical award criterion 1 states: Training of authorities (i.e. National Competent [...]
|
1. Please note that point g) of the technical award criterion 1 refers to section 2.2.1 of Terms of reference [...]
|
05/01/2023
|
|
10
|
Is it necessary to set the price for the 30 countries listed in the financial offer or only for the 10 [...]
|
Yes, for all countries listed in the financial offer as it has not yet been decided, at this stage, which [...]
|
05/01/2023
|
|
9
|
Financial offer: 1. Based on the rates that we will include in the price table, the financial offer tab [...]
|
1. The financial offer is linked to the two scenarios; however, the financial offer should cover all [...]
|
05/01/2023
|
|
8
|
In case of handwritten signature, should we ship to EIOPA the original documents? By when and to which [...]
|
Please refer to document titled “Invitation to tender”, “§1. Submission of tenders” for a detailed answer [...]
|
05/01/2023
|
|
7
|
Given that no purchases will be required by shoppers, can you please clarify whether post-purchase assessments [...]
|
No post-purchase assessments will be needed. The focus will be on pre-sale, selling process.
|
21/12/2022
|
|
6
|
The terms of reference make mention of a Common Mystery Shopping Methodology, developed by EIOPA. Could [...]
|
The methodology is not a public document and it will only be shared with the awarded contractors. However [...]
|
20/12/2022
|
|
5
|
Is purchasing to be required? If so, what will be purchased? What is the approved ‘cancellation’ process [...]
|
No purchase is required.
|
15/12/2022
|
|