21
|
The reply to question N.1 was posted 3 weeks after it was submitted. The response to this question was [...]
|
The deadline for submission of offers will not be extended. As mentioned in the answer to Question 1 [...]
|
17/08/2022
|
|
20
|
Our understanding from the tender specifications is that the Work Package 3 requires the contractor to [...]
|
Tenderers are required to fulfil all selection criteria described in section 3.2 of the Tender Specifications [...]
|
17/08/2022
|
|
19
|
We are a UK based company and have considerable experience in the provision of Assessment Centres, having [...]
|
As indicated in Section 2.2 of the tender specifications, participation in this call for tenders is, [...]
|
11/08/2022
|
|
18
|
We assume that you have already worked with a provider to create test material. Could we please have [...]
|
Please note that all information required to prepare a tender is available in the procurement documents [...]
|
11/08/2022
|
|
17
|
Could we please enquire about your preferred method of contractual review? Would you prefer a marked-up [...]
|
As indicated in point 2 of the invitation to tender, submission of a tender implies acceptance of all [...]
|
11/08/2022
|
|
16
|
We assume that UK-registered companies are eligible to apply as per the WTO regulations. Please confirm [...]
|
On the basis of section 2.2 of the tender specifications and section IV.1.8 of contract notice 2022/S [...]
|
09/08/2022
|
|
15
|
Could you please provide a copy of the CV format? There is one we have downloaded from the system, however [...]
|
Referring to our reply to question 4, Section 3.2.3 of the tender specifications requires all tenderers [...]
|
09/08/2022
|
|
14
|
Am i right in saying that any tests used for pre-selection are already in place and therefore not part [...]
|
Correct. This tender procedure does not include reasoning tests.
|
07/08/2022
|
|
13
|
Please can you clarify what is meant by ‘The price for the CBI discussion with the Selection Board and [...]
|
Correct. For competency based interviews, the contractor will, for each competition, discuss with the [...]
|
07/08/2022
|
|
12
|
Do you have behavioural indicators for your competencies and are these levelled? If they are levelled [...]
|
Yes, we have behavioural indicators for our competency framework, usually 5 anchors per competency. The [...]
|
07/08/2022
|
|