7
Dear Sir/Madam, regarding the Instructions for Candidates for the above project, we have two questions [...]
Q1. The Contracting Authority confirms that reference period is 6 years (from 1st of January 2016 up [...]
19/08/2022
6
Dear Sirs, regarding to the above mentioned tender we will ask you if it would be enough to submit the [...]
The submission should follow instruction to candidates (Section 15) and should include: - The duly filled [...]
19/08/2022
5
Is the reference period 6 years or 3 years? Or is the reference period comprised between 6 years and [...]
The Contracting Authority confirms that reference period is 6 years (from 1st of January 2016 up to the [...]
19/08/2022
4
Do the 100 km length of the railway and the value of 1,3mln € and 250k € refer to the single project, [...]
The fees values of 1.3 MEUR for criteria 3(a) and 250,0000 EUR for criteria 3(b) are minimums for each [...]
19/08/2022
3
1. considering that during this period most of the staff has been on annual leave, would you please consider [...]
1. The Contracting Authority confirms that the submission deadline remains unchanged. 2. The scope of [...]
19/08/2022
2
Point 13.3. of Selection criteria for Technical capacity of tenderer requires among others experience [...]
The Contracting Authority confirms that references presented under criteria 3(b) shall relate to Environmental [...]
19/08/2022
1
One of our references is completed on August 2022. The contract was signed in October 2016. The financial [...]
It is the responsibility of the bidder to demonstrate the value of the fees of the projects presented [...]
19/08/2022