53
Request for deadline extension: We would be grateful if you would consider extending the submission deadline [...]
In order to respect the organisational planning of the procedure, the contracting authority will not [...]
27/01/2023
Answered
52
Factoring in design has resulted in yearly cost differences across the duration of the contract. Based [...]
Concerning the design costs, see question 51. Cells F25 and F26 “TOTAL PRICE to be considered for the [...]
24/01/2023
Answered
51
Pricing: As per European Commission instructions we have provided a per person cost factoring in design [...]
The initial design of the Assessment centres, Development, Programmes and Multi-source feedback mechanisms [...]
24/01/2023
Answered
50
Section 4.2: "A Comprehensive proposal for the organisation of an information session for DG HR senior [...]
It means that the tenderer has to explain how it would take into consideration (integrate) the results [...]
23/01/2023
Answered
49
Additional information on senior management selection procedures: The link towards additional information [...]
The information can be found under https://commission.europa.eu/jobs-european-commission/job-opportunities [...]
23/01/2023
Answered
48
We understand that there is a common competency framework across all both roles. We need to know whether [...]
As indicated under sub-criterion 1.2, we need specific exercises for each of the managerial level, i.e [...]
23/01/2023
Answered
47
Award criteria: Regarding subcriterion 3.3, do we understand correctly that an example of a report both [...]
You can submit an example in English OR in French, one language version will be sufficient. The « recommended [...]
23/01/2023
Answered
46
Multi-source Feedback: Please clarfy what is the difference between Lot 2 Development for participants [...]
Part 2 refers to development programmes offered to 4 target populations – among them, "senior managers [...]
20/01/2023
Answered
45
Further clarity please to a previous question: Original question: Can we use a sample role to provide [...]
The Competency Framework is the same for both managerial levels and the tenderer is invited to provide [...]
20/01/2023
Answered
44
Clarity needed to Q36 in the Q&A: Annex 6: Can we provide different pricing for single person assessments [...]
Question36 The price to be indicated in Annex 6 is the price (P) per participant attending an assessment [...]
20/01/2023
Answered