43
|
The binary built-up layer in the golden standard is defined as a geotiff file with 0 for no built-up [...]
|
The document “Annex 7. Annex 1 to tec specs 1365” explains the details of the geospatial data, and in [...]
|
11/10/2022
|
|
42
|
How are project-related publications regulated in this call? For example, may partial results be published [...]
|
Question21
|
06/10/2022
|
|
41
|
In the Document, Tender Specification -Part-1 , Sections 2.4.1 and 2.4.2, can you please advice the following [...]
|
1. There is no limit on the number of members of the joint tenderers. 2. There is no limit in the number [...]
|
26/09/2022
|
|
40
|
In the Document - Tender Specification -Part-1 , section - 4.2: What information do we need to provide [...]
|
Tenderers are required to provide any other relevant information regarding the offer.
|
26/09/2022
|
|
39
|
The EO data (like Sentinal 1, Sentinal 2, or any other Public available EO data) will be used as input [...]
|
The EO data have to be provided by the contractor. Copernicus Sentinel data is available on various platforms [...]
|
26/09/2022
|
|
38
|
After reviewing the tender specifications, we have noticed that most of the workload belonged to the [...]
|
The payment arrangements described in article I.6 of the draft framework contract refer to each specific [...]
|
21/09/2022
|
|
37
|
Can you please confirm that the Non-EU countries eligible for participation are those that signed the [...]
|
Yes, we confirm. The GPA is applicable to this call for tenders.
|
13/09/2022
|
|
36
|
In Section 5.6 of the EN-6 document, the 10m product should reach an MAE level better than 0.08. However [...]
|
As described in the Tender Specifications Part 2 TecSpecs 1365 in section 5.5.1 (pp. 16-17), the “technical [...]
|
13/09/2022
|
|
35
|
For the benefit of community and due to administrative efforts, given the large amounts of material to [...]
|
The deadline will be extended. A corrigendum of the Contract notice with the new deadline and a new date [...]
|
13/09/2022
|
|
34
|
Concerning section 3.2.3. Technical and professional capacity of the Tender Specifications Part 1 - Criterion [...]
|
Criterion 1 requires at least two projects and 3 fields are requested. Therefore, one single project [...]
|
08/09/2022
|
|