22
|
How much time will elapse between the award of the contract and the mobilization time / start of initial [...]
|
The award and subsequent signature of the Framework Contract will not lead directly to any work implementation [...]
|
13/04/2023
|
|
21
|
In the Operation of Sensory Panel, two categories of services are mentioned: simple and complex product [...]
|
“Simple product test” and “complex product test” are described in section 1.4.2 of the call for tender [...]
|
12/04/2023
|
|
20
|
We are an independent body in the TIC industry, who covers many scopes of business area and provide services [...]
|
The presence of conflicting interests will be examined only during the evaluation phase based on the [...]
|
31/03/2023
|
|
6
|
A - What is the defined timeline for billing? Is it task-specific? Is it per month or per year? B - When [...]
|
A. The contractor (or leader in the case of a joint tender) will have to send an invoice for the interim [...]
|
30/03/2023
|
|
7
|
A - Sums are going to be committed at the start of the project. Are advance payments made, or advances [...]
|
A. Pre-financing (or advance payment) is not applicable to this FWC. The FWC foresees that the contractor [...]
|
30/03/2023
|
|
19
|
H - Penalties: understanding its application in case of joint and several subcontracting, is that correct [...]
|
H. If you mean contractual penalties, please refers to point question B.
|
30/03/2023
|
|
18
|
G - Possibility of reducing prices in the event of default on page 33: can we propose an alternative [...]
|
G. No. The provisions of the Framework contract are not subject to negotiation and cannot be modified [...]
|
30/03/2023
|
|
17
|
F – On page 25 authorisation for subcontracting to be requested from the buyer in case of need, is this [...]
|
F. Changes concerning subcontractors identified in the tender (withdrawal/replacement of a subcontractor [...]
|
30/03/2023
|
|
16
|
E – Does the agreement in case of a consortium (annex 3) have to be signed before the submission of the [...]
|
E. Yes. Please refers to Annex 1 - List of documents to be submitted with the tender or during the procedure
|
30/03/2023
|
|
15
|
D - What types of contracts are possible between each member of a consortium?
|
D. Please refers to paragraph 2.4 - Ways to submit a tender: how can economic operators organise themselves [...]
|
30/03/2023
|
|