13
In section 5.2.2. "evidence of economic and financial capacity", point C, "a statement of overall turnover [...]
In this point, we ask for a statement of the overall turnover of your company of the past 3 years and [...]
06/09/2011
12
The check list of the required documents includes the "power of attorney", which should be submitted [...]
You can do both, if it is feasible to have one document signed by all partners in time, this is the best [...]
06/09/2011
11
Would it be possible to apply from Switzerland?
Yes, as mentioned under point II.1.7) of the contract notice, this contract is covered by the Government [...]
02/09/2011
10
In the case of a joint bid, all the group members have to necessarily sign only one document? Or can [...]
Yes, if needed, every partner in the joint bid can sign the power of attorney separately on the condition [...]
02/09/2011
9
Should the final one-day conference be located in Brussels or could it take place in another European [...]
!! IMPORTANT : Unlike the reply to this question published on 26/8/2011, it must be noted that the tenderers [...]
01/09/2011
8
Should the final one-day conference be located in Brussels or could it take place in another European [...]
Yes the final conference have to be held in Brussels.
26/08/2011
7
Can a member of the TSG or an institution represented in the TSG participate in this Tender?
Yes, a TSG member or an institution represented in the TSG could participate in the call for tender.
26/08/2011
6
Annex 6.7. III TSG INDICATORS 2011 lists a number of measures that can only be obtained through primary [...]
Task 4 regards the implementation of the system of indicators and the toolkit in selected pilot destinations [...]
19/08/2011
5
With regards the test implementation in selected destinations (task 4): based on the envisaged starting [...]
Implementation of the system of indicators and the toolkit in selected pilot destinations (task 4) can [...]
19/08/2011
4
Dear Ladies and Gentlemen, we are wondering about the conference organisation. The specifications state [...]
No, participants will have to pay for their own overnight accommodation.
16/08/2011
3
Are there any restrictions with regards to the number of nationalities of the Experts participating in [...]
No restrictions nor requirements are imposed on the number of experts or the number of nationalities [...]
12/08/2011
2
Dear Madam/Sir, would it be possible to apply from Turkey?
Yes, as Turkey participates in the CIP programme, applications from Turkey can be accepted.
25/07/2011
1
We would like to ask a clarification in relation to the Letter of Intent of subcontractor. We would like [...]
You can put the letter(s) of intent in section one, together with the information on the tendering organisation [...]
20/07/2011