32
“Can we assume that, with reference to Article I.4 "Appointment of the Contractor and Implementation [...]
Correct. Article 17 of the ToR precedes and will be applied in the final contract to be signed.
06/03/2023
31
T2: Can the reference to address the policy gaps be from corporate clients (not governments) where policies [...]
Only if the proof can be a public available deliverable or a deliverable that can be shared as annex [...]
06/03/2023
30
T1: Can you please confirm that as references to projects supplied for core services, we can provide [...]
References can be foresight exercises or other references specifically on the analysis of future and [...]
06/03/2023
29
Are tenderers allowed to use references from customers outside European Union ? Is the tenderer allowed [...]
Q1:Are tenderers allowed to use references from customers outside European Union? A1: Yes Q2:Is the tenderer [...]
06/03/2023
28
If the experts profiles are part of the selection criteria, can these profiles be met through the combined [...]
No, the proposed individual to cover a profile (either senior or junior) shall meet all the requirements [...]
06/03/2023
27
T3: Kindly confirm that the minimum of two junior and two senior expert satisfying the mandatory requirements [...]
Under T3 it is referred that “the tenderers must demonstrate the capacity to build, coordinate and manage [...]
06/03/2023
26
The scenario mentions a one-week time requirement to draft a preliminary report following a disruptive [...]
It is the expected timeframe to deliver the preliminary report.
03/03/2023
25
Supplier would like to limit the liability to 100% of the value of the specific contract. This is more [...]
The General Conditions of our model contracts are not negotiable.
03/03/2023
24
It is unclear for supplier how the reduction in price is being calculated. It should be clear beforehand [...]
Reductions in price and liquidated damages are contractual penalties to be applied in cases of bad quality [...]
03/03/2023
23
Supplier would like to request the penalty according to article II.15.1 to not exceed 10% of the value [...]
The General Conditions of our model contracts are not negotiable.
03/03/2023