15
13. For specific contracts of 6 months and beyond are further interim payments possible?
For each specific contracts/order form exceeding 6 months duration, the contractor may request an interim [...]
05/04/2016
14
12. Framework Service Contract clause 1.4.3 indicates that final payments can be applied for at the end [...]
This is the reason why, for payments above 6 months, an interim payment up to 30% is envisaged.
05/04/2016
13
11. Framework Service Contract clause 1.4.2 indicates that on contracts of over 6 months interim payments [...]
This is defined with the contractor when the order form/specific contract is issued in the light of the [...]
05/04/2016
12
10. Technical Specifications P10 of 52 - Service Type 6. Would you expect the framework supplier to carry [...]
Not foreseen. The technical studies generally consists in the development of link budget analysis with [...]
05/04/2016
11
9. Technical Specifications P9 of 52 - Service Type 5. What is the frequency of the ITU or CEPT meetings [...]
This service is used in conjunction with service type 2, 3 and 4 to take into account longer meetings [...]
05/04/2016
10
8. Technical Specifications P9 of 52 - Service Type 4. What is the frequency of the 3 days CEPT meeting [...]
See CEPT website for the calendar of meetings. In average, we requested attendance of 6 CEPT meetings [...]
05/04/2016
9
7. Technical Specifications P9 of 52 - Service Type 3. What is the frequency of the ITU 10 day meeting [...]
See ITU website for the calendar of meetings. In average, we requested attendance of 2 ITU-R 1 week meeting [...]
05/04/2016
8
6. Technical Specifications P9 of 52 - Service Type 2. What is the frequency of the ITU 1 week meeting [...]
See ITU website for the calendar of meetings. In average, we requested attendance of 3-4 ITU-R 1 week [...]
05/04/2016
7
5. Technical Specifications P8 of 52 - Service Type 1. Can you please confirm if this means to review [...]
Technical Specifications P8 of 52 - Service Type 1. Can you please confirm if this means to review and [...]
05/04/2016
6
4. Can you provide a full schedule of the meetings that take place over the course of the year that EDA [...]
Calendar of meetings are publically available on the ITU and CEPT websites. The tenderer shall be in [...]