Details zur Ausschreibung

Titel:
Transport- und sonstige Dienstleistungen zur logistischen Unterstützung in der E...
Öffentlicher Auftraggeber:
European Commission, DG for European Civil Protection and Humanitarian Aid Opera...
Datum der Veröffentlichung im TED:
06/07/2016
Frist für den Eingang von Angeboten:
26/08/2016
Status:
Geschlossen
Filter-Parameter anzeigen

Results per page: 10 | 25 | 50 29 Fragen found, displaying all Fragen .
# Frage Antwort Datum der letzten Veröffentlichung Status
1
To ensure that we fully understand your price structure, could you confirm the following: For the emergency [...]
Yes, correct. The total price to be invoiced is composed of the cost of the service + Fixed fee + variable [...]
12/07/2016
2
Is there a possibility that the contractor will have to provide services post-termination and therefore [...]
The contractor shall not be requested to provide services after the termination of the framework contract [...]
26/07/2016
3
Dear, The precise contractual link in the Europass website is not listed for us to upload our CVs. Please [...]
Here's the link to Europass : https://europass.cedefop.europa.eu/
26/07/2016
4
Dear, Please confirm if you have a preferred billing location. Since we intend to have our global headquarter [...]
The contractor (or leader in the case of a joint tender) signatory of the FWC will have to issue the [...]
26/07/2016
5
Dear sirs, would you be able to kindly provide past volume data (number of shipments/weight per transport [...]
We have no specific statistics about the weight transported. From 2013 to 2015, there has been 24 requests [...]
26/07/2016
6
Could this be amended to read: The FWC enters into force on 16 December 2016 or when signed by both parties [...]
The intention of the contracting authority is to have the new FWC entering into force on 16 December [...]
26/07/2016
7
Could the definition of ‘Fraud’ also make a cross-reference to the rights of the contractor under Clause [...]
Note that the provision you are referring to is a provision of the general conditions and cannot be amended [...]
26/07/2016
8
Could the contracting authority please consider adding the following provision as the last sentence to [...]
Note that the provision you are referring to is a provision of the general conditions and cannot be amended [...]
26/07/2016
9
Could the contracting authority please advise the specific areas of Clause II.13 that will apply to the [...]
Please refer to Article I.10 of the special conditions of the draft contract related to the results of [...]
26/07/2016
10
Can this clause be amended to read ‘…..in accordance with good industry practice and…..’ and so deleting [...]
Note that the provision you are referring to is a provision of the general conditions and cannot be amended [...]
26/07/2016
11
Will global freight forwarders and air charter brokers with wide carrier networks and road transport [...]
The contracting authority understands that it is not feasible to list all possible transport operators [...]
26/07/2016
12
Under 6.2. Draft Framework Contract / II.6. LIABILITY there are no reference to any Standard Trading [...]
Note that you are referring to a provision of the general conditions of the FWC. Unless specificalilly [...]
26/07/2016
13
Will the contractor have the opportunity to incorporate their Standard T&Cs where it is not appropriate [...]
The contractor will not have the opportunity to incorporate their Standard T&Cs. Terms and Conditions [...]
26/07/2016
14
Could the following wording be added to the end of this clause after FWC: “… unless caused by the failure [...]
Note that the provision you are referring to is a provision of the general conditions and cannot be amended [...]
01/08/2016
15
Can the contracting authority please advise the maximum level of general comprehensive insurance cover [...]
It is required for the framework contractor to be covered, independently of any consideration concerning [...]
01/08/2016
16
Can we implied that the Warsaw convention won't be applied in this tender? since the liability is to [...]
Unless specifically defined in specific points of the techinical specifications, the Warsaw and/or Montreal [...]
01/08/2016
17
Can the contracting authority please advise the maximum level of general comprehensive insurance cover [...]
See answer for question 15.
01/08/2016
18
Could this clause be amended with additional wording to read: “The contractor is liable for any direct [...]
Note that the provision you are referring to is a provision of the general conditions and cannot be amended
01/08/2016
19
Could this clause be amended with additional wording to read: “A party is not liable for any delay, loss [...]
Note that the provision you are referring to is a provision of the general conditions and cannot be amended
01/08/2016
20
Could this clause be amended with additional wording to read: “The contracting authority is not liable [...]
Note that the provision you are referring to is a provision of the general conditions and cannot be amended
01/08/2016
21
Would the service provideer will be penalized in case of force majeur? Regards
In case of force majeure, the service provider should immediately inform the contracting authorithy. [...]
01/08/2016
22
Is the requirement for liability insurance to cover damage up to EUR 500 million in the 2nd paragraph [...]
The liability insurance is relevant for the contractor.
01/08/2016
23
As a freight forwarder, we regularly subcontract to a number of different vehicle operators that do not [...]
No, the contracting authority will accept only liability insurance covering damage up to EUR 500 million [...]
01/08/2016
24
The formula for liquidated damages for each day of delay has the potential to enforce a large financial [...]
Note that the provision you are referring to is a provision of the general conditions and cannot be amended
01/08/2016
25
What is the maximum figure expected to be in terms of ‘the total amount of the relevant specific contract [...]
I don't understand the question. No specific ceiling is foreseen as "total amount of the relevant specific [...]
01/08/2016
26
Is the requirement for liability insurance to cover damage up to EUR 500 million in the 2nd paragraph [...]
See answer to question 22
01/08/2016
27
As an air charter broker that uses many different airlines, is it acceptable to the Contracting Authority [...]
No, the insurance is requested for the entire duration of the framework contract. (5.2.3 f page 35)
01/08/2016
28
Quoting from the FWC //The contractor is liable for any loss or damage caused to the contracting authority [...]
The "relevant specific contract" corresponds to a unique set of shipments corresponding to a specific [...]
04/08/2016
29
Insurance departement is asking more information on the theater of operations, the shipment détails in [...]
As war risks are very specific, they may be covered by an insurance quoted separately at time of shipment [...]
22/08/2016