# Question Answer Last publication date Status
12
There is a huge discrepancy between the level of detail provided for the preparation of the hypothetical [...]
Lots 1 through 3 relate to impact assessments, whereas lot 4 relates to ex post evaluation. Although [...]
09/11/2012
11
There is a huge discrepancy between the level of detail provided for the preparation of the hypothetical [...]
Lots 1 through 3 relate to impact assessments, whereas lot 4 relates to ex post evaluation. Although [...]
09/11/2012
10
The treatment of other costs is not clear in the tender documentation. The General Conditions (article [...]
Article 1.3.4. "Reimbursement of expenses" of the Special Conditions states "Not applicable", so reimbursable [...]
09/11/2012
9
Categories of personnel are not defined in the Tender Specifications. Both the table on page 21 (related [...]
The definition of the categories of personnel is left to the tenderers and is to be specified in the [...]
09/11/2012
8
As a result of the lack of categorization of experts and of the indeterminacy of the hypothetical cases [...]
The definition of the categories of personnel was left to the tenderers (see reply to question 2012-139143 [...]
09/11/2012
7
A similar problem emerges in connection with reimbursable expenses. On page 43 it is said that the price [...]
As specified in section 5.3, the contracts will be awarded to the most cost-effective tenders, which [...]
09/11/2012
6
The Annex Section of the Tender Specifications include the ‘Financial and Economic Capacity Overview [...]
The form should be filled in by all.
31/10/2012
5
Would it be acceptable to incorporate the experts’ statement that they are able to work and produce reports [...]
Yes, it is acceptable to incorporate the experts' statement of being able to work and produce reports [...]
29/10/2012
4
Would it be acceptable to have scanned signatures in CVs?
Yes, it is acceptable to have scanned signatures in CVs.
29/10/2012
3
On page 32, the Tender Specifications make reference to a ‘Statement confirming the validity of the tender [...]
Yes, the statement can be included in the letter of submission signed by the leading firm.