16
|
Art. II.15.1 Delay in Delivery We propose to change this specific (incorrect in our opinion) formula [...]
|
The Art. I.9.1. of the Special Conditions takes precedence over Art. II. 15.1. of the General Conditions [...]
|
05/07/2016
|
|
15
|
Art. II.5 Communication some references to Art. I.8 are wrong, should be Art. I.6
|
Correct. The reference in the quoted contractual clause should be Art. I .6. Please note that it is a [...]
|
05/07/2016
|
|
14
|
Art. I.9 Liquidated Damages are unlimited We propose a limitation to 5% of the Contract value.
|
Frontex does not agree with the proposed changes. Please note that the appropriate contractual clause [...]
|
05/07/2016
|
|
13
|
Art. I.7.1 Applicable law shall be FRONTEX law complemented by the laws of Poland. FRONTEX Law is unknown [...]
|
Art 1.7.1 of the draft contract refers to the Union law not Frontex law.
|
05/07/2016
|
|
12
|
Due to records present in Point 1.2.1 in Annex II_Terms of Reference in range of product maximum age [...]
|
Frontex agrees that in order to receive the best accuracy products it is accepted that no more than 30% [...]
|
05/07/2016
|
|
11
|
Are there any specifications regarding the height reference system?
|
Default height reference system of DSM product. Units: meters.
|
14/06/2016
|
|
10
|
Is PLN the account currency so that a European contractor with bank accounts denominated in EUR and USD [...]
|
Article 1.5 of the draft Service Contract has been amended to: ‘payments shall be made to the Contractor [...]
|
14/06/2016
|
|
9
|
Due short time of product delivery - 8 weeks after the contract is in force (point 1.5, Annex II_Terms [...]
|
No
|
14/06/2016
|
|
8
|
Will the contracts for delivery satellite images be accepted as contracts similar to the subject of this [...]
|
Yes
|
14/06/2016
|
|
7
|
In case of the coverage contains specific area excluded from supply due to law, the time of delivery [...]
|
In such cases, where it is justified that due to a national law some permit(s) are to be obtained to [...]
|
14/06/2016
|
|
6
|
Does the “Products made of the DEM” (point 1.4, Annex II_Terms of Reference) will not contain any height [...]
|
The most probable derived product is a shaded relief, which will not contain height information.
|
14/06/2016
|
|
5
|
Can you please shortly acknowledge that the completely edited and finalized DSM product has to be delivered [...]
|
We acknowledge it.
|
14/06/2016
|
|
4
|
Is our Interpretation correct, that the most recent date for data acquisition for each area has to be [...]
|
Yes
|
14/06/2016
|
|
3
|
Does the net value of 300.000 € for contracts performed in the last 3 years refer to each single contract [...]
|
The required value of 300,000 EUR refers to each single contract which has been performed (completed) [...]
|
14/06/2016
|
|
2
|
Due to short time of delivery and large amount of data, we conclude to extend delivery time at least [...]
|
The requested delivery time, set in Annex II- Terms of Reference, shall be respected, unless due to national [...]
|
14/06/2016
|
|
1
|
The records present on point 1.3 and 1.4 [ Annex II_Terms of Reference] compared with Article I.8 and [...]
|
The previously published version of the draft contract (Annex VI-draft contract) is currently replaced [...]
|
14/06/2016
|
|