11
|
“Starting from the existing pages in the Natura 2000 web-site, the contractor will further develop them [...]
|
A new website, which will be part of Europa, will be created and maintained by the contractor, using [...]
|
13/07/2016
|
|
10
|
Can the Commission confirm if the experts are paid for their role on the project? If so what is the scale [...]
|
The experts that will be involved in the project are proposed by the tenderer and paid under the contract [...]
|
07/07/2016
|
|
9
|
Can the Commission confirm the timing of the Annual Award Ceremony?
|
The Natura 2000 Award ceremony in taking place on or around 21st of May
|
07/07/2016
|
|
8
|
Can the commission please confirm that the scope of the contract covers the award and coordination of [...]
|
The contract will cover the next cycle of the Award and will not cover any initiatives related to the [...]
|
07/07/2016
|
|
7
|
A. Can you please confirm the number of expert meetings (this is currently stated as 2 – 3) but for pricing [...]
|
A. The number of expert meetings has to be defined by the tenderer in order to ensure efficient processing [...]
|
06/07/2016
|
|
6
|
Does the indicative weighting of the intput for the different tasks, outlined on page 23 of the tender [...]
|
The indicative weighting of the intput for the different tasks, outlined on page 23 of the tender specifications [...]
|
06/07/2016
|
|
5
|
A. Can you confirm that each award cycle contains a minimum of 9 events (6 Local events, minimum of 2 [...]
|
A. The exact number of events and meetings will be defined by the tenderer. Information about the expected [...]
|
06/07/2016
|
|
4
|
Can you confirm that the current expert panel is to be revised for the current award cycle
|
Before each award cycle is launched, the contractor shall propose and set up an evaluation panel composed [...]
|
06/07/2016
|
|
3
|
Can you confirm that the budget outlined in the tender specifications is for one year or for one full [...]
|
The budget alocation oulined inthe tender specification is for the duration of the contract which is [...]
|
06/07/2016
|
|
2
|
A. We would like to confirm that the contract runs for 24 months, which covers one cycle. B. Can you [...]
|
A. The tasks should be completed within 24 months of the signature of the contract. The execution of [...]
|
06/07/2016
|
|