11
“Starting from the existing pages in the Natura 2000 web-site, the contractor will further develop them [...]
A new website, which will be part of Europa, will be created and maintained by the contractor, using [...]
13/07/2016
10
Can the Commission confirm if the experts are paid for their role on the project? If so what is the scale [...]
The experts that will be involved in the project are proposed by the tenderer and paid under the contract [...]
07/07/2016
9
Can the Commission confirm the timing of the Annual Award Ceremony?
The Natura 2000 Award ceremony in taking place on or around 21st of May
07/07/2016
8
Can the commission please confirm that the scope of the contract covers the award and coordination of [...]
The contract will cover the next cycle of the Award and will not cover any initiatives related to the [...]
07/07/2016
7
A. Can you please confirm the number of expert meetings (this is currently stated as 2 – 3) but for pricing [...]
A. The number of expert meetings has to be defined by the tenderer in order to ensure efficient processing [...]
06/07/2016
6
Does the indicative weighting of the intput for the different tasks, outlined on page 23 of the tender [...]
The indicative weighting of the intput for the different tasks, outlined on page 23 of the tender specifications [...]
06/07/2016
5
A. Can you confirm that each award cycle contains a minimum of 9 events (6 Local events, minimum of 2 [...]
A. The exact number of events and meetings will be defined by the tenderer. Information about the expected [...]
06/07/2016
4
Can you confirm that the current expert panel is to be revised for the current award cycle
Before each award cycle is launched, the contractor shall propose and set up an evaluation panel composed [...]
06/07/2016
3
Can you confirm that the budget outlined in the tender specifications is for one year or for one full [...]
The budget alocation oulined inthe tender specification is for the duration of the contract which is [...]
06/07/2016
2
A. We would like to confirm that the contract runs for 24 months, which covers one cycle. B. Can you [...]
A. The tasks should be completed within 24 months of the signature of the contract. The execution of [...]
06/07/2016
1
When would the European Commission plan for the contract to start?
Once the contract is awarded and signed by both parties (contractor and Commission), the contract can [...]
04/07/2016