54
In relation to the response to Question 40, is it allowed to annex the draft communication strategy to [...]
The submitted technical offer shall not exceed a total of 50 pages (without annexes). Any relevant, additional [...]
18/08/2016
53
If two companies in a joint tender do not fulfill all criteria of 2.3.4 but together they do, what should [...]
In Annex 5 you can tick NO in individual boxes but the lead tenderer must tick YES in the final box VII [...]
18/08/2016
52
In the case of a joint tender, must each member of the consortium fill in this document ?
Each Annex states under the heading who should complete it. For ANNEX 5 - DECLARATION ON HONOUR ON EXCLUSION [...]
18/08/2016
51
Will the tenderer be in charge of identifying and inviting speakers and should possible travel costs [...]
The European Commission identifies the speakers for the applicant workshop (usually consisting of representatives [...]
11/08/2016
50
There are 12 indicator areas for the EGCA evaluation and 6 categories for the EGL evaluation. Does it [...]
As stated on page 26 of the relevant tender specifications, all 12 EGCA experts "review the received [...]
11/08/2016
49
Thank you very much for your response regarding the stands. However, if in Question 9 your response is [...]
These refer to material to be sent for the stand / as part of the stand, such as communication material [...]
11/08/2016
48
Must the contractor carry the costs of the catering for these two events?
Please refer to page 20 of the relevant tender specifications "Costs for the rental of the venue (and [...]
10/08/2016
47
Could you please let us know the dimensions (LxWxH = Length x Width x Height) of the stands? (p. 19 of [...]
Question 9
10/08/2016
46
In the section 2.3.4 Technical and professional capacity criteria and evidence a. Criteria and evidence [...]
Section "2.3.4 Technical and professional capacity criteria and evidence" of the relevant call for tender [...]
10/08/2016
45
Do projects references provided for evidence (evidence A1, A2, A4) have to be for finished projects only [...]
Project references should be for finished projects
09/08/2016