22
|
Regarding the development of online tools and systems to be delivered under 4.3.1a) - Evaluation advisory [...]
|
The key software/tools to be used for the delivery of the ESS services currently are: Cap4DeV and EVAL [...]
|
21/09/2016
|
|
21
|
Please confirm whether the foreseen incidental expenditure budget can be utilised for the development [...]
|
No new IT tools/software will be developed as part of the ESS service. The list of services under 4.3.1a [...]
|
20/09/2016
|
|
20
|
Please can you confirm whether expenditure verification costs are reimbursable under this contract and [...]
|
In line with Article 28 of Annex B – 'Draft contract and special conditions' of the tender dossier, no [...]
|
20/09/2016
|
|
19
|
We take good note of the provisions included in the Instructions to Tenderers (section 3.8) and in the [...]
|
The provisions regarding conflict of interest in the tender dossier refer to situations that can be encountered [...]
|
20/09/2016
|
|
18
|
The Instructions to Tenderers requests that signatures in original copies of documents must be in blue [...]
|
The tender submission form and the declarations contained within must be original. The signatures required [...]
|
20/09/2016
|
|
17
|
On p. 8 of the Instructions to Tenderers it is stated that “any expert working on an EU/EDF-finance project [...]
|
The clause that states the dates in the Statement of Exclusivity and Availability 'must not overlap with [...]
|
08/09/2016
|
|
16
|
We are requested to use the template provided to complete the section called ‘Organisation and Methodology [...]
|
As indicated in the Tender Section 4.3(2) on page 9 , you should use font 12 Times New Roman.
|
08/09/2016
|
|
15
|
On p. 6 of the Instructions to Tenderers it is stated that the “tenderer must have completed at least [...]
|
If the contract is related to a project that has been finalised, and the contract has been closed and [...]
|
07/09/2016
|
|
14
|
The Technical Evaluation Grid does not include any information on how CVs of core team experts are going [...]
|
The CVs of the proposed core team will be evaluated under selection criteria, please see point 4.2.2. [...]
|
07/09/2016
|
|
13
|
Do members of the core team need to be EU nationals? If not, will the EC assist in securing work visas [...]
|
The core team can be non-EU nationals; there is no restriction on the nationality of the core team. The [...]
|
07/09/2016
|
|
12
|
Is prior evaluation experience with DEVCO required to take part in the tender?
|
We would like to clarify that prior DEVCO evaluation experience is not required for the purpose of this [...]
|
05/09/2016
|
|
11
|
Could you please confirm that eventual weaknesses in the methodological approach to potential conflict [...]
|
Please see answer to question 10.
|
02/09/2016
|
|
10
|
Could you please confirm that no potential conflict of interest of the tenderer will automatically revert [...]
|
Inability to adequately report and avoid/mitigate possible professional conflict of interest will results [...]
|
02/09/2016
|
|
9
|
Conflict of interest: We take good note of the provisions included in the Instructions to Tenderers ( [...]
|
1) Yes. Please see answer 1. 2) Yes. Please see answer 1. 3) All candidates have to demonstrate their [...]
|
02/09/2016
|
|
8
|
In the technical capacity criteria, it is stated that the language of contract must be either French [...]
|
Such a contract would be acceptable if the principal language of the contract was French or English ( [...]
|
30/08/2016
|
|
7
|
Please confirm whether it would be possible to include ongoing projects to fulfil the criteria in Section [...]
|
In the Instructions to Tenderers, section 4.2.2, states that "the tenderer must have completed at least [...]
|
29/08/2016
|
|
6
|
On p. 15-16, the ToR list requirements for potential non-core experts. Are we right to assume that it [...]
|
The tender documents set out which CVs are required at the tender stage. CVs of non-core experts were [...]
|
29/08/2016
|
|
5
|
Question 1: On p. 9 the ToR state that „The QA Panel experts will have to demonstrate no current or previous [...]
|
The Quality Assurance Panel is a specific service identified as a 'further service' Section 4.3.1 Please [...]
|
29/08/2016
|
|
4
|
Could you please confirm that no conflict of interest will involve, a priori, Framework Contractors leader [...]
|
The onus is on the tenderer to produce a methodology to ensure conflict of interest, including potential [...]
|
29/08/2016
|
|
3
|
On p. 13 the ToR state that “one full-time post (with the exception of the Team Coordinator) could be [...]
|
A further line can be added to ensure you can show two part time posts (with days showing 440 for each [...]
|
29/08/2016
|
|
2
|
On p. 12 the ToR mention January 2016 as intended start date of the contract. Are we right to assume [...]
|
The estimated start date of the contract is January 2017. Please see Instructions to Tenderers point [...]
|
22/08/2016
|
|
1
|
We are leaders of the consortium providing consultancy services within FWC LOT1 COM- Evaluation (strategic [...]
|
No tender is excluded from applying a priori. However all candidates have to notify in their offer the [...]
|
17/08/2016
|
|