Call for tenders' details

Title:
‘Observation and analysis of trans-Alpine freight traffic flows by road and by r...
Contracting authority:
European Commission, DG Mobility and Transport (MOVE)
TED publication date:
14/07/2016
Time limit for receipt of tenders:
05/09/2016
Status:
Closed
Show filter parameters

Results per page: 10 | 25 | 50 10 Questions found, displaying all Questions .
# Question Answer Last publication date Status
10
Capacity to work in 4 languages is required. Could you please confirm if maximum 3 projects can be listed [...]
The important aspect is that the tenderer is able to prove his capacity to work in all four languages [...]
30/08/2016
9
For EU projects (for example Alpine Space projects or EUTC projects) it may be difficult to get a statement [...]
In extraordinary cases where the required statements by clients are not available for whatever reason [...]
30/08/2016
8
Shall projects listed to satisfy criterion A4 be the same used to satisfy criteria A1 and/or A2?
Projects which satisfy criterion A4 and which happen to also satisfy criteria A1 and/or A2 MAY also be [...]
30/08/2016
7
Shall reports provided be supported by a statement issued by the client as for criteria A1, A2 and A4 [...]
Statements issued by the clients are only required for the project references which are to be provided [...]
30/08/2016
6
3.2.3 Economic and financial capacity, Criterion F2, Ratio between assets and liability above 1: According [...]
The accounting equation or balance sheet equation on which criterion F2 is based should be read as follows [...]
26/08/2016
5
Considering that today the methodology exists and works well from several years (and that all the datas [...]
The methodology describes the way in which the tenderer intends to carry out the work. Criterion 1 of [...]
25/08/2016
4
Is it allowed to list more project references than actually needed to fulfill all criteria of point 3.2.4 [...]
It is possible to list more project references than actually required under the criteria to prove the [...]
23/08/2016
3
According to Criterion A1, the tenderer must prove experience in the field of freight transport analysis [...]
The tenderer is required to provide references for at least three projects covering all the fields mentioned [...]
23/08/2016
2
Terms of reference, page 18, point 3.2.3 Economic and financial capacity criteria, Criterion F2: Applies [...]
No, this criterion does not apply to subcontractors. It should be noted that in case of subcontracting [...]
18/08/2016
1
Point 3.2.4 mentions "statements issued by the clients". What is exactly expected here and which form [...]
The statements from the clients must 1) include all the elements mentioned in section 3.2.4 of the tender [...]
16/08/2016