Call for tenders' details

Title:
Project to extend and modernise the Konrad Adenauer Building in Luxembourg - lot...
Contracting authority:
European Parliament, DG Infrastructure and Logistics (INLO)
TED publication date:
08/11/2016
Time limit for receipt of tenders:
25/01/2017
Status:
Closed
Show filter parameters

Results per page: 10 | 25 | 50 24 Questions found, displaying all Questions .
# Question Answer Last publication date Status
24
55.1.5 As per item 1.1, but EI90, height approx. 2.35 m (PV5); without acoustic requirements [ml] Installation [...]
24/01/2017
22
Could you elaborate on the concept of "valeur hors terrain et hors sol du projet " in document " PE_- [...]
It refers to the overall cost of the aboveground part of the project (without subsoil) and without the [...]
19/01/2017
23
Following your reply to question 22, we have interpreted that the " montant des travaux réellement exécutés [...]
The " montant des travaux réellement exécutés par le soumissionnaire '' refers to the part of the value [...]
19/01/2017
21
Hello. Are the documents referred to in points 13.1 to 13.3 to be supplied with the tender, or are they [...]
1) In accordance with point 13.7 of the Specifications, ‘... the European Parliament accepts the declaration [...]
03/01/2017
20
Hello. Can you provide us with an area in which to unload lorries close to the goods lifts? Will the [...]
No, there will not necessarily be an unloading area next to the goods lifts. Horizontal transfer from [...]
03/01/2017
19
55.1.6 Melamine coating for the partitioning The description states that the cladding should be approximately [...]
For the section of frame above the door, the panel height must be roughly 42 cm, elsewhere the panels [...]
03/01/2017
18
1.8. Door components (7.) Climatic classification for wooden doors Minimum requirement to be met/evidenced [...]
Confirmation: Climatic classification 2b in accordance with DIN EN 12219 for wooden doors.
03/01/2017
16
1.8.(2.) Wooden door The description makes a distinction in thickness between the door leaves according [...]
Tenderers must indicate in the tender what thickness of door panel they consider necessary to achieve [...]
03/01/2017
15
1.8.(2.) Wooden door Contradiction between the thickness mentioned in this article and detailed plan [...]
Tenderers must indicate in the tender what thickness of door panel they consider necessary to achieve [...]
03/01/2017
14
1.8.(2.) Wooden door Composition of the door leaf: Lacquered finish contradicts the description in the [...]
The doors must be glazed.
03/01/2017
13
1.6.7. Definition of colours Can you explain: (2.) Light-reflection index between partition door frame [...]
(2.) Tactile contrast definition = luminance contrast: >= 30 LRV. It is a difference in brightness [...]
03/01/2017
12
1.4. Physical building constraints 1.4.4. Fire stability The description of the fire resistance classification [...]
All wall and emergency escape compartment coverings must have a fire resistance rating of at least Euroclass [...]
03/01/2017
11
1.4. Physical building constraints 1.4.4. Fire stability The fire resistance of the various removable [...]
Firewalls are to be provided in the positions shown under items description CA14.
03/01/2017
10
1.2.2. Overall description / door (4.) List of doors the text refers to documents KAD____-06TPP_____- [...]
The document referred to is not part of the file. Reason: the doors are equipped only with a handle, [...]
03/01/2017
9
Part E. Supporting documents necessary for the verification of compliance with the selection criteria [...]
1) The model PE_-160321-CA_-Economic_viability.xlsx has been replaced by model PE__-160525-CA__-Turnover_Operating [...]
03/01/2017
8
1. How is the delivery of the removable partitioning organised? Are there goods lifts to transport them [...]
1. See reply to the question of 14.12.2016; 17.46. 2. For chapter 1 of CA14, the cost of the doors is [...]
03/01/2017
7
What percentage deductions should be made in calculating proportional charges such as for electricity [...]
Works management costs are reimbursed by the European Parliament, including for lot 2, logistics, waste [...]
03/01/2017
6
Question 8: The total wall loading is given here as 500kg/m on both sides. Is the specification with [...]
Loads should comply with the DIN 4103-1 standard (in relation to DIN 18183-1) for installation zone 2 [...]
03/01/2017
5
Question 7: What difference in pressure [Pa] should there be between corridor and office?
The maximum head loss between corridor and office is 25 Pa.
03/01/2017
4
According to the CTPG general and special technical specifications p.16, 1.4.4 ‘Stability on exposure [...]
4. All wall and emergency escape compartment coverings must have a fire resistance rating of at least [...]
03/01/2017
3
Question 1: Could a coated wooden door of the same surface quality as the wall plate be offered in place [...]
1. Variants are not permitted. 2. Variants are not permitted. 3. Variants are not permitted.
03/01/2017
2
Dear, Is it possible submit a tender without the full dossier (expired on 24th November)? which kind [...]
Tenders may be submitted until 25 January 2017. As indicated in section VI. 3. of the contract notice [...]
03/01/2017
1
Dear Sir/Madam, my questions concern the request for ‘one (1) reference in respect of a new non-residential [...]
1) Yes, supplies may have been delivered in batches, but for the same new tertiary building project completed [...]
03/01/2017
17
1.8.(3.) Frame Contradiction between the description of an aluminium frame and detailed plan KAD____- [...]
Intended as block-frame. Hereto see additionally plan attached (KAD____-07ACL002_____-TB01-692-EXE-CA-BPE [...]
22/12/2016