1
|
- On page 25 of the Terms of Reference, the "Simulated Request for Services 1" lists two alternative [...]
|
Contact points must be provided for the EU countries which are not covered by the tenderer's project [...]
|
22/05/2017
|
|
2
|
In the terms of reference and on the list of "Annexes to the tender specifications", Annex X is mentioned [...]
|
Annex X has been added.
|
23/05/2017
|
|
3
|
We have noticed that all the section references mentioned in the Annex VIII (Document check list) don't [...]
|
Document updated
|
24/05/2017
|
|
4
|
We understand that Annex VII has to be calculated on the cumulated values for the last two years for [...]
|
Annex VII should be provided for the last year for which accounts have been closed. Paragraph: Tenderers [...]
|
24/05/2017
|
|
5
|
We understand that the CV do not have to be signed. Are we correct?
|
CVs shall be presented in accordance with the Commission recommendation on a common European format for [...]
|
24/05/2017
|
|
6
|
On page 20 of the ToR, it is mentioned that six (6) values and five (5) ratios should be calculated. [...]
|
Once you fill in the values in the first tab of the excel file "Simplified presentation" the scores are [...]
|
24/05/2017
|
|
7
|
Please advise if there is a targeted page limit for each hypothetical case study description
|
Tender Specifications, page 25: Each simulated exercise should be of maximum 30 pages.
|
24/05/2017
|
|
8
|
Reference is made to Section 3.6.B – Criterion B.1 of the Tender Specifications. Both the contract manager [...]
|
Yes, it can be any type of fact finding work that covers at least 15 member states.
|
29/05/2017
|
|
9
|
Dear Sir/Madam, - On page 25 of the Terms of Reference, the "Simulated Request for Services 1" lists [...]
|
In order to allow fair comparison, please provide a technical proposal on the second study only: "Study [...]
|
29/05/2017
|
|
10
|
Re the "Simulated Request for Services 1" for Lot 2 ‘Study supporting the impact assessment on food waste [...]
|
Question9
|
29/05/2017
|
|
11
|
On page 25 of the Tender Specifications, it is mentioned in the column referring to the Simulated Request [...]
|
Question9
|
29/05/2017
|
|
12
|
Dear Sir/Madam, We urgently need an answer concerning the question below (sent on 23.05.2017) as we would [...]
|
Question9
|
29/05/2017
|
|
13
|
Re the "Simulated Request for Services 2" for Lot 1 - ‘Study supporting the impact assessment on joint [...]
|
Indeed, tenderers should prepare a proposal assuming a new package of policy options. Tenderers should [...]
|
29/05/2017
|
|
14
|
Re the "Simulated Request for Services 2" for Lot 2 ‘Study supporting the impact assessment on food waste [...]
|
Indeed, tenderers should prepare a proposal assuming a new package of policy options. Tenderers should [...]
|
29/05/2017
|
|
15
|
Reference is made to Section 1.2 - Participation of the Tender Specifications. We understand that the [...]
|
If during the implementation of the FWC an amendment is necessary, this will be dealt in line with the [...]
|
30/05/2017
|
|
16
|
Please clarify if organisations established in the United Kingdom can participate in a consortium applying [...]
|
Organisations established in the UK can participate in this tender.
|
30/05/2017
|
|
17
|
To our understanding, it is possible to include subcontractors who provide eligible references or experts [...]
|
It is possible to include subcontractors who provide eligible references or experts in line with point [...]
|
30/05/2017
|
|
18
|
It is mentioned in page 21 of the Tender Specifications that the tenderer must provide references delivered [...]
|
The tenderer should provide references of projects delivered and not ongoing. To allow for a clear cut [...]
|
30/05/2017
|
|
19
|
To our understanding a subcontractor is not required to complete the excel file (available in the document [...]
|
The subcontractor is not required to send the excel file on simplified presentation viability. Subcontractors [...]
|
01/06/2017
|
|
20
|
Could you confirm if the proof of timely submission is the date of postage via courier service of applicants [...]
|
As indicated in the invitation to tender "Receipt is understood as the time at which the tenderer hands [...]
|
02/06/2017
|
|
21
|
To our understanding the core team can include experts who are not in-house / permanent staff of the [...]
|
The selection criteria relating to the team delivering the service are described in section 3.6.B. of [...]
|
02/06/2017
|
|
22
|
Following the clarification provided on "Subject: financial capacity of subcontractors " , to our understanding [...]
|
The CVs of experts are evaluated as part of the selection criteria relating to the team delivering the [...]
|
02/06/2017
|
|
23
|
Dear DG Santé, we would like to enquire into the deadline of the proposal. Unless we missed a prior information [...]
|
A corrigendum will be soon published that will extend the deadline from 19/6 to 26/6.
|
06/06/2017
|
|
24
|
Noting that clarification was provided on the dummy bid requirements on 29 May and that these are very [...]
|
Question23
|
06/06/2017
|
|
25
|
We consider that the given deadline of one month for this complex Framework Contract is very tight. In [...]
|
Question23
|
06/06/2017
|
|