Results per page: 10 | 25 | 50 12 Questions found, displaying 1 to 10.[First/Prev] 1, 2 [Next/Last]
# Question Answer Last publication date Status
12
I would like to confirm if it is possible to tender only for one or two of the 3 lots.
Yes, it is possible to submit a tender only for Lot 1 or Lot 2 or Lot 3.
28/03/2017
11
I would like to confirm that in the instance of a company responding to all three lots, the response [...]
Considering the fact that more than one tenderer can be awarded a contract, we prefer to keep the technical [...]
27/03/2017
10
Please confirm that upon submission of the Tender no evidence is required based on the quotation below [...]
Yes, we confirm that no evidences are required at the stage of tender submission.
23/03/2017
9
Will the EC evaluate each "Lot" separately such that an award could be given to more than one entity [...]
Yes, each lot will be evaluated separately, thus the contracts might be awarded to different entities [...]
23/03/2017
8
Financial Offer. Assuming a Tenderer submits a response for all 3-Lots, does the Financial Offer need [...]
You need to submit separate offers for each lot, since they will be evaluated separately.
23/03/2017
7
In the Tender, aside from the cover letter there is no specific format describing how to present the [...]
If the outline you propose covers all aspects and tasks required in the technical specifications as described [...]
16/03/2017
6
Can a copy of "EN-3.0.Administrative Annex.pdf" be provided in MS Word format?
No, this document will not be provided in MS Word format.
16/03/2017
5
Being a US company we need to petition the US Internal Revenue Service for a certified form stating all [...]
The country on the petition should be The Netherlands. A signed statement from your CPA would be sufficient [...]
16/03/2017
4
Is there is a specific reason the final meeting for Lot-2 is a different week that Lot's 1 and 3? If [...]
They can be held during the same week.
16/03/2017
3
The Kick-Off meeting being held during Week-1 will apply to all Lots, correct?
Yes.
16/03/2017