12
It is important to know possible maximum intensity and length of a service cycle (e.g. 4 experts for [...]
It is up to the contractor how to organise the work in cooperation with the EEA. However, the intra-muros [...]
20/04/2017
Answered
11
Concerning the management of environmental data and product repositories (6.2 – scope of the contract [...]
The EEA provides the technical infrastructure for repositories. In 2016 there were produced approximately [...]
20/04/2017
Answered
10
With reference to the place of performance of the services could you please provide us with an indication [...]
As specified in Annex I - Tender specifications, the EEA will try as much as possible to organise intra-mural [...]
20/04/2017
Answered
9
Please explain the requirement for technical and professional capacity concerning application of environmental [...]
As specified in the tender specifications, tenderers shall provide a description of their environmental [...]
20/04/2017
Answered
8
With reference to the types of services to be provided please provide clarifications on the following [...]
The content of each order form will depend on the specific needs of the contracting authorities at the [...]
12/04/2017
Answered
7
In section 6 of the tender specifications document it is stated that “In drawing up their bid, tenderers [...]
Thank you for noticing. Please see the updated Annex 6 to the tender specifications that has been uploaded [...]
07/04/2017
Answered
6
We are intending to incorporate two different subcontractors to our tender. The first one will be providing [...]
We confirm that your understanding is correct.
03/04/2017
Answered
5
In the case a tenderer provides additional content (e.g. annexes) complementing / supporting the information [...]
In order to ensure equal treatment of all tenderers you are advised to respect the maximum limit of characters [...]
28/03/2017
Answered
4
For those texts in which the Tender Specifications state a maximum number of characters, does this maximum [...]
No, spaces are not considered.
28/03/2017
Answered
3
Items c) (QA accreditation) and f) (environmental policy) should be separate for each consortium member [...]
Your understanding is correct. For points (d) and (e) tenderers should provide a description for the [...]
28/03/2017
Answered