15
|
Can you please confirm that criteria 3 (see page 12 of Annex 1) refers to the management, organisation [...]
|
Yes, it is confirmed. Criteria 3 should be understood as adequacy of the management, organisation and [...]
|
03/05/2017
|
|
14
|
According to award criteria 2 the tenderer has to draft a Communication Plan (see page 12 of Annex 1) [...]
|
Annex V. SFR. Strategy paper / technical proposal. Point 2. General Communication Plan: “Tenderers are [...]
|
03/05/2017
|
|
13
|
Could you please confirm that point 2. of the technical proposal, “General Communication Plan” is supposed [...]
|
Annex V. SFR. Strategy paper / technical proposal. Point 2. General Communication Plan: “a general communication [...]
|
03/05/2017
|
|
12
|
Could you please confirm that the economic and financial capacity evidence that is presented in the Standard [...]
|
Please see reply to question 10.
|
02/05/2017
|
|
11
|
Based on the Standard Reply Form, could you please confirm that the third parties' form will be submitted [...]
|
Yes, the third party files only needs to be submitted by the leader of the tendering group.
|
02/05/2017
|
|
10
|
In the SRF (annex V) some of the documents are indicated as not to be presented at the submission date [...]
|
Documents which, in the SRF, are indicated as “document to be prepared as it may be requested in a very [...]
|
02/05/2017
|
|
9
|
The declaration on honour on exclusion and selection criteria states that “in the case of joint tenders [...]
|
Please reply to question 8
|
02/05/2017
|
|
8
|
The declaration on honour on exclusion and selection criteria states that “in the case of joint tenders [...]
|
Distinction between joint tenders and subcontracting is presented in points 4.1 and 4.2 of the “Guidebook [...]
|
02/05/2017
|
|
7
|
Dear Madam or Sir, Please specify if companies based in the USA are eligible for participation in this [...]
|
Unfortunately, companies based in the USA are not eligible for participation in this call. Participation [...]
|
02/05/2017
|
|
6
|
We do not agree that 32 days are available to tenderers. This calculation assumes that our employees [...]
|
As indicated in the previous reply, the duration is expressed in calendar days, as usual in the financial [...]
|
21/04/2017
|
|