Call for tenders' details

Title:
Local recovery centre.
Contracting authority:
European Investment Bank (EIB)
TED publication date:
18/05/2017
Time limit for receipt of tenders:
26/06/2017
Status:
Closed
Show filter parameters

Results per page: 10 | 25 | 50 16 Questions found, displaying all Questions .
# Question Answer Last publication date Status
16
PC's MANAGEMENT SOFTWARE • Is the software for PC’s management (connected to the internal network of [...]
The EIB will provide the software necessary to manage the Laptops and PCs delivered by the Bank.
09/06/2017
15
IMAGE • How many images will need be managed ?
We do not expected to have more than 2 images as the EIB is aiming to work with the lowest possible number [...]
09/06/2017
14
PC's AND LAPTOPS REPLACEMENT • In the RFP, every 3 years the Provider needs to upgrade all PC’s / laptops [...]
At the EIB, PCs and laptops of key users are normally replaced after 3 years. The goal of this requirement [...]
09/06/2017
13
FLEXIBILITY In the RFP: the Tenderer shall offer the opportunity to increase or reduce the scope of the [...]
Neither a minimum nor a maximum are defined. The requested flexibility is expected not to exceed 10%. [...]
09/06/2017
12
KPI’s • Can you please provide EIB’s expected KPI’s ?
As the KPIs are dependent on the proposed solution, it is expected that the exact list of KPIs will be [...]
09/06/2017
11
TECHNICAL RESOURCE(S) DEDICATED TO THE MAINTENANCE OF THE RECOVERY SOLUTION • Who manages the Resource [...]
The task management of the Technical Resource(s) will be done by EIB. The Technical Resource will mainly [...]
09/06/2017
10
PACKAGES For a good understanding, please confirm : • Package 1 : EIB provides all IT equipment and all [...]
Service Package 1: EIB will provide all IT equipment and furniture. Service Package 2: The provider has [...]
09/06/2017
9
CONTRACT DURATION Please confirm : is this a 3-year contract which can be renewed (at the end of the [...]
Yes, this is correct.
09/06/2017
8
PRODUCTION DATE In the RFP, starting date of the production phase : 01/10/2017. Considering this is an [...]
The current contract runs until 31st December 2017. Therefore the starting date of the new contract in [...]
09/06/2017
7
AGENDA: Could you detail the timetable of the RFP? For example schedule of:  the commercial discussion [...]
Below is just an indicative timetable of the process after the opening of tenders: - Evaluation of tenders [...]
09/06/2017
6
The recovery positions shall be reachable within max. 30 minutes driving (under normal traffic). Is there [...]
Please refer to Section 1.8 of the Terms of Reference, "... The overall goal is therefore to minimise [...]
09/06/2017
5
Are there any prerequisites or contradictions for the location of the Recovery Center ?
Please refer to Section 1.8 of the Terms of Reference, "... The proposed locations shall not have high [...]
09/06/2017
4
Service Package 1 (2.2.2.2) and 2 (3.2.1.4) defines between 70 and 85 desks. Does EIB have specific requirements [...]
In general bigger rooms require a lower density of desks. The values given below should be applied as [...]
01/06/2017
3
In Package 1 (2.2.5), how many parking spaces shall be available during invocation ?
EIB requires (Section 2.2.5) that, under normal conditions, 5 parking positions are available on a 24 [...]
01/06/2017
2
Point 8.3.3 “Requirement 2: Capacity of the tenderer to provide the full scope of services, i.e. all [...]
"The tenderer has to be able to offer all 4 service packages. If a tenderer does not offer all 4 service [...]
01/06/2017
1
Location : it is specified 1.8 that “the recovery positions shall be located outside of Luxembourg’s [...]
As outlined in Section 1.8 of the Terms of Reference, "...The overall goal is therefore to minimise the [...]
01/06/2017