47
|
“EN-Annex 4 - Terms of Reference” 4.1.1.2.1c Security Operation Center off-site Can you please provide [...]
|
This question is not exactly relevant. We do not consider that a ratio number of EPS / staffing can be [...]
|
29/11/2017
|
|
46
|
“EN-Annex 4 - Terms of Reference”, Sec. 5.6.2 Service Level Requirement, KPI9 Please: • clarify how the [...]
|
*To measure the availability of the SOC, we would like to monitor the availability of a backend component [...]
|
29/11/2017
|
|
45
|
With reference to Appendix 3 – Table of Staff Profiles. In case a candidate has several years of experience [...]
|
No, we do not confirm your understanding. For a proposed profile (candidate) the tenderer can only put [...]
|
29/11/2017
|
|
44
|
With reference to Appendix 7. Please consider the following example: A vendor’s initial price (list price [...]
|
Reply to sub-question 1: We confirm Reply to sub-question 2: We confirm Reply to sub-question 3. We confirm [...]
|
29/11/2017
|
|
43
|
With reference to Question 9 and 22, we understand that in case of a company A (the Tenderer) which relies [...]
|
Yes, we confirm that your understanding is correct.
|
29/11/2017
|
|
42
|
With reference to Annex 8 and Annex 9. Our understanding is that these Annexes are signed upon the contract [...]
|
Yes, we confirm that your understanding is correct.
|
28/11/2017
|
|
41
|
Our understanding is that in case of a joint offer (submitted by a Consortium of two companies) the “ [...]
|
The “Appendix 1 - Economic and Financial Capacity Overview Form” should be filled in and signed by each [...]
|
28/11/2017
|
|
40
|
Referring to: - “EN-Annex 4 - Terms of Reference.pdf”, page 43, Section “7.3.1.6 Quality of proposal [...]
|
Yes, we confirm your understanding.
|
28/11/2017
|
|
39
|
Making reference to “Terms of Reference”, 1. Introduction, first paragraph where it is stated “The European [...]
|
a) Occasionally, EIB and EIF join forces concerning procurements in which both entities have common interests [...]
|
28/11/2017
|
|
38
|
In case we rely on a subcontractor to fulfil the technical and professional capacity, our understanding [...]
|
Yes, we confirm your understanding, except that the subcontractors are not required to submit Annexes [...]
|
28/11/2017
|
|