13
The draft Contract material of the Invitation to Participate includes items that need to be discussed [...]
We understand that your question refers to the contract documentation in Annex 4.2 to the Specifications [...]
12/01/2018
Answered
2
Would you be so kind and allow us an additional delay of 2 weeks for the delivery of the proposal? We [...]
The Agency has analysed your request and is processing a corrigendum to the contract notice of this procedure [...]
19/12/2017
Answered
12
We kindly request an extension by two weeks of the due date of phase I: the submission of the request [...]
The Agency has analysed your request and is processing a corrigendum to the contract notice of this procedure [...]
19/12/2017
Answered
11
Considering the end of the year holiday season upcoming, would ECHA be so kind to give ten extra working [...]
The Agency has analysed your request and is processing a corrigendum to the contract notice of this procedure [...]
19/12/2017
Answered
10
Supplier is requested to provide references of successful provision of services (e.g. Annex 4.3.3.4). [...]
Candidates may use any project or contract reference that meets the requirements of the selection criteria [...]
18/12/2017
Answered
9
Our understanding is that in case we rely on an entity of the same group, we only need to mention this [...]
The Candidate’s Administrative Data form must be completed with the names of all the economic operators [...]
15/12/2017
Answered
8
How are the various selection criteria items (Financial, Technical and Service Delivery Capacity) valued [...]
The sole purpose of the selection criteria is to determine whether a Candidate has the capacity necessary [...]
15/12/2017
Answered
7
With reference to the Non Disclosure Agreement, we understand that this document must be provided by [...]
The Non-Disclosure Agreement must be submitted by the Candidate or all partners in a joint request to [...]
15/12/2017
Answered
6
With reference to the continuous page numbering of the annual accounts, would it be acceptable to staple [...]
We can confirm that the described method is acceptable.
15/12/2017
Answered
5
With reference to the continuous page numbering on page 14 of the Specifications phase I and II, could [...]
We can confirm that continuous page numbering per section is accepted.
15/12/2017
Answered