1
|
For ease of submission, can we insert our answers to the questions provided in annex XI in a word document[...]
|
Yes you can.
|
17/07/2018
|
|
2
|
• Page 5/8 of the ‘Conditions for submitting a tender’ document: ‘All the documents requested in points[...]
|
1.1 Yes we confirm. 1.2 Yes you have to provide those documents with your offer. 2.1 Yes we confirm. [...]
|
17/07/2018
|
|
3
|
Page 19/21 of the Specifications document: ‘Depending on the nature, quantity or scale and purpose of[...]
|
1) That sentence is part of the template for the European Parliament, which is used to cover all types[...]
|
17/07/2018
|
|
4
|
On page 20 of the tender specifications it states that (for each case study) tenderers need to obtain[...]
|
Yes you are right, this is a typo: the minimum is 11 points, not 13. We have uploaded a corrected version[...]
|
17/07/2018
|
|
5
|
Article I.4 of the draft framework contract refers to interim payments. Can you please confirm that pre-financing[...]
|
We confirm that pre-financing payments are not foreseen. There are no limitations to the number of interim[...]
|
17/07/2018
|
|
6
|
1. Should the technical offer be signed or only the economic offer? 2. In the case of a joint tender,[...]
|
1. We expect at least the signature of a cover page and the signature of the price list. You do not need[...]
|
30/07/2018
|
|
7
|
Point 8 of the specifications refers to “on-site repair services in case of operational failures”. To[...]
|
Typical scenario: The contractor is asked to develop an app that manages the Facebook live interviews[...]
|
30/07/2018
|
|
8
|
The document library includes Annex VII - Financial data sheet. Could you please clarify the following[...]
|
1) Yes we confirm that you can only provide those figures for the last two years. 2) You can include [...]
|
30/07/2018
|
|
9
|
Chapter 5 - I - Administrative Part of the tender specifications states the title of each section of [...]
|
1) Annex VI can be included in section 1. 2) All documents used for the selection criteria should be [...]
|
30/07/2018
|
|
10
|
In the case of subcontracting, in which envelope should we introduce Annex VI?
|
Annex VI should be in the administrative part. Further details on technical aspects of subcontracting[...]
|
30/07/2018
|
|
11
|
You can confirme that the three parts of the proposal: administrative, technical and economic, are presented[...]
|
Yes, you can put the three sections in the same envelope (be careful about the double envelope for confidentiality[...]
|
31/07/2018
|
|
12
|
We noticed that the document library includes Annex IV - Financial identification form - supplier. Could[...]
|
1) Yes, the Annex IV -Financial Identification Form should be submitted with the tender. 2) The Annex[...]
|
02/08/2018
|
|
13
|
Point 2) in question 8 refers to where in the administrative part of the tender Annex VII should be included[...]
|
Yes, the Annex VII should be in Section 3 of the Administrative part.
|
02/08/2018
|
|
14
|
1) Could you please indicate in which of the following sections of the Administrative part of the tender[...]
|
1) Annex IV should be included in Section 3 (Selection criteria) of the "Administrative" part. 2) Annex[...]
|
07/08/2018
|
|
15
|
Could you confirm the Case studies documents should be included in the Technical Part? In addition to[...]
|
The case studies documents should be included in the Technical part. The Technical part should include[...]
|
20/08/2018
|
|
16
|
1. In terms of the 3 'parts', could they be presented for example together in one folder, but separated[...]
|
1. The three parts mentioned in point 5. of the Conditions: I - Administrative Part, II – Technical part[...]
|
20/08/2018
|
|
17
|
Can tenderers use different staff profiles providing they come from Annex X - Price List?
|
Yes.
|
22/08/2018
|
|
18
|
The documents can be signed with electronic signature for the two electronic copies, or we need to scan[...]
|
The European Parliament does not recognize any type of electronic signature, so only the "pen to paper[...]
|
22/08/2018
|
|
19
|
Labels A3 and A5 are asking for similar explanation (status reporting and meetings). Could you please[...]
|
Label A3 is about the way and kind of reporting methods ( what kind of meetings are planned), and Label[...]
|
28/08/2018
|
|
20
|
According to the conditions for submitting a tender, part 'II - Technical Part' should be made up of [...]
|
We confirm that the supporting documents are outside the 400 word limit, and should be treated separately[...]
|
28/08/2018
|
|