21
|
Bidder requests clarification regarding the extent to which Results are intended to include the Pre-existing [...]
|
Results may include both newly created elements and pre-existing materials on which there will be usually [...]
|
08/05/2018
|
|
20
|
As a software engineer, I am trying to gauge what is required to allow users to be able to register in [...]
|
Users would be able to register with their EU login once the Platform is set up. Regarding how to integrate [...]
|
08/05/2018
|
|
19
|
In the bid introductory letter, paragraph 3, the instruction says: ' ... the inner envelope must also [...]
|
Strictly speaking, as explained in the terms of reference, pages 5 and 6, the technical offer is part [...]
|
03/05/2018
|
|
18
|
Could it be that the section 2.4 mentioned on page 37, at ´1. Quality and appropiateness of the proposed [...]
|
Indeed, as it is clear from the detailed references in the sub-criteria, section 2.3 is meant, which [...]
|
27/04/2018
|
|
17
|
I posted 2 questions on April 19 and April 20 . To date, I haven't received any reponse about my enquiries [...]
|
Please refer to the answers provided to questions No 14 and No 15.
|
25/04/2018
|
|
16
|
Your answer to question 13 means that it would be acceptable to allocate a budget of 1.4M€ (to give a [...]
|
The reply provided to the question 13 makes clear that for Tasks 1, 2 and 4 the indicative cost estimated [...]
|
25/04/2018
|
|
15
|
Can you confirm the aplication of the Finaltial and Administrative Framework Agreement (FAFA) between [...]
|
No, the Financial and Administrative Framework Agreement between the European Community and the United [...]
|
25/04/2018
|
|
14
|
What do you mean by "as well as to the people"? There will be papers from H2020 that will be published [...]
|
The Section 2.3.3 d) on page 22 of the specifications requires transparency regarding the costing of [...]
|
25/04/2018
|
|
13
|
In a previous question on the budged of the contract, it is said in the answer that: The Annex 8, page [...]
|
The maximum total value of the contract is 6 400 000.00 EUR, as is stated in the contract notice at ted.europa.eu [...]
|
23/04/2018
|
|
12
|
The deadline for this tender is clearly May 18, 2018, however, I cannot find details of the format for [...]
|
Please refer to the published invitation letter, point 3.
|
23/04/2018
|
|