11
|
Referring to the question published yesterday about the deadline to submit the hard copy of the documents [...]
|
Since the publication of the call on 18/04/2018, tenderers have had sufficient time for collecting and [...]
|
30/05/2018
|
|
10
|
Criterion A4 demands the tenderer to prove capacity to work in the official languages of the countries [...]
|
Please see the answer to the question number 9.
|
29/05/2018
|
|
9
|
Evidence A4 requires the tenderer to "provide references for at least two completed projects in the last [...]
|
In order to fulfil the selection criterion A4, the tenderer must prove capacity to work in the official [...]
|
29/05/2018
|
|
8
|
No specific adress is given in the Invitation to Tender, for the documents (the originals of the declaration [...]
|
In the case where tenderers do not use an electronic signature, they must send by post, at the latest [...]
|
29/05/2018
|
|
7
|
Dear, in Annex 2.2 it is stated that the table should be filled 'without referring to other sections' [...]
|
Yes, this is acceptable. In Annex 2.2 - Technical capacity, the tenderer should describe how the tenderer [...]
|
28/05/2018
|
|
6
|
Dear, as a proof of criterion A1 2 completed projects are asked. Would it also be fine if the project [...]
|
As a general rule, the references for projects need to be for completed and delivered projects in order [...]
|
25/05/2018
|
|
5
|
For the purposes of the coverage of the case studies (Task 4), is UK considered an EU Member State? Shall [...]
|
Q1:For the purposes of the coverage of the case studies (Task 4), is UK considered an EU Member State [...]
|
21/05/2018
|
|
4
|
It is unclear whether the total liability of contractor in case of liquidated damages and liability for [...]
|
Please see the answer to the question number 2.
|
14/05/2018
|
|
3
|
Evidence for criterion A2 states that: "tenderer must provide references for at least 2 publications [...]
|
Yes, "the references for at least 2 publications containing a socio-economic impact analysis, preferably [...]
|
14/05/2018
|
|
2
|
From article II.6.3 it is not clear who determines if there is “gross negligence” or “willful misconduct [...]
|
In compliance with point 2. Of the invitation to tender, please note that “Submission of a tender implies [...]
|
14/05/2018
|
|