Renseignements sur l'appel d'offres

Intitulé:
Prestation de services informatiques externes
Pouvoir adjudicateur:
European Parliament, DG Innovation and Technological support (ITEC)
Date de publication sur TED:
04/08/2018
Date limite pour la réception des offres:
20/09/2018
Statut:
Fermé
Masquer les paramètres de filtrage
Paramètres de filtrage


Results per page: 10 | 25 | 50 327 Questions found, displaying 1 to 25.[First/Prev] 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14 [Next/Last]
# Question Réponse Date de dernière publication Statut
327
We would like to know if it would be possible for us, as an Austrian Company, to take part in the tender [...]
As stated in the invitation letter, no response will be given to any request for additional information [...]
18/09/2018
326
Dear Sir or Madam, In the situation where one company depends on the references of a (sister) company [...]
As stated in the invitation letter, no response will be given to any request for additional information [...]
17/09/2018
325
With regards to the Analyst profile in Lot 3, could you please define how many years of experience the [...]
Regarding the experience, the set of CVs must demonstrate that the tenderer is able to address the technical [...]
14/09/2018
324
(I) According to the Q&A #251 “The implementation of the solution is included in the scope but not [...]
The Case Study 3 is purely done for evaluation and doesn't reflect the reality in the EP's Environment [...]
14/09/2018
323
Part F of the Technical Specifications (p. 7) states: “3.1.2 Wide Area Networks (WAN) Parliament's main [...]
There is a mix of 1GB and 10GB linked to the throughput needs, and site/building capacity. 10 GB between [...]
14/09/2018
322
Please provide us with specific information about: (a) the aggregate (all links) specific TCP/IP throughput [...]
10 GB between all datacenters. a) 10 GB b) 10 GB c) 10 GB
14/09/2018
321
The Case Study requirements require “List of deliverables, with samples (maximum 1 A4 page each additionally [...]
The overall limit for the case study is 10 A4 pages, including the method to validate the deliverables [...]
14/09/2018
320
With reference to your answer to QA#196, we understand that this is applicable to framework contracts [...]
As stated in the invitation letter, no response will be given to any request for additional information [...]
14/09/2018
319
With reference to Part B of Technical Specifications – Profiles, when experience of “J2EE” is requested [...]
As stated in the invitation letter, no response will be given to any request for additional information [...]
14/09/2018
318
It is our understanding that the professional experience requirement for the PSAR profile is fulfilled [...]
As stated in the invitation letter, no response will be given to any request for additional information [...]
14/09/2018
317
With reference to “Section 5. Quality assurance and control mechanisms” of Part G to Technical Specifications [...]
As stated in the invitation letter, no response will be given to any request for additional information [...]
14/09/2018
316
With reference to “Section 5. Quality assurance and control mechanisms” of Part G to Technical Specifications [...]
As stated in the invitation letter, no response will be given to any request for additional information [...]
14/09/2018
315
The sheer volume of submitted questions (310 at this specific moment) should be strong indication to [...]
As stated in the invitation letter, no response will be given to any request for additional information [...]
14/09/2018
314
With reference to Q&A No 297 and the reference in the tendering specifications document regarding [...]
As stated in the invitation letter, no response will be given to any request for additional information [...]
14/09/2018
313
With reference to document Conditions of Submitting a tender, we read: “The first part of the tender [...]
As stated in the invitation letter, no response will be given to any request for additional information [...]
14/09/2018
312
Due to text limitation, this question will be divided into two: Following the answer to our question [...]
During the execution of this contract, the winner will respect the project methodology of the participating [...]
13/09/2018
311
In addition to this guide, dedicated training sessions about the methodology are organised.”. As example [...]
Please see answer Question193
13/09/2018
310
For the following statement (see §3.3 of EN-02A01G ITS19 - Part G to Technical Specifications - Technical [...]
See answer to Question309
13/09/2018
309
For the following statement (see §3.3 of EN-02A01G ITS19 - Part G to Technical Specifications - Technical [...]
The set of CVs must demonstrate that the tenderer is able to address the technical areas covered by the [...]
13/09/2018
308
For the following statement (see §3.3 of EN-02A01G ITS19 - Part G to Technical Specifications - Technical [...]
The set of CVs must demonstrate that the tenderer is able to address the technical areas covered by the [...]
13/09/2018
307
Could a Gantt chart be added as an Annex to the case study, not counting toward the 20 page limit? Although [...]
No. In Part C to Tech Spec – Technical evaluation questionnaire, page 61, it is defined that "The maximum [...]
13/09/2018
306
With reference to your answer to QA# 228 and the instructions provided in Annex V to Tender specifications [...]
Yes, see answer to Question295.
13/09/2018
305
With reference to Q&A 271, our understanding is that anny project plan (planning schedule) can be [...]
Your understanding is incorrect. Please refer to the general instructions regarding the page limitation [...]
13/09/2018
304
With reference to your answer to QA#184, we understand that the reference will be considered to have [...]
Your understanding is incorrect. The requirement is that the final acceptance by the Client has occurred [...]
13/09/2018
303
With reference to “Annex 1 - ITS19 CV TEMPLATE” of the document “Part G to Technical Specifications, [...]
Your understanding is incorrect. See answer to Question223
13/09/2018