14
Can you please confirm that the experts category B3 – Experts in rail expertise should instead read B4[...]
Confirmed. It should be read as follows B1 - Project Manager: At least 10 years' experience in project[...]
20/08/2018
Answered
13
Regarding Evidence A1, there is no indication concerning the number of references expected. Is there [...]
The applicants must deliver as many references as they think can be enought to prove their capability[...]
20/08/2018
Answered
12
If the scope of work of a project covers more than one technical and professional capacity criterion,[...]
Yes, it can be acceptable. The applicant is reminded to clearly identify in its application which criterion[...]
20/08/2018
Answered
11
We believe the ERA is an important party for the success of this study. Can you please clarify if DG [...]
DG Move will support coordination between ERA and the contractor, nevertheless it can not be held responsible[...]
20/08/2018
Answered
10
Can you please clarify if the mentioned business case refer to the opportunity costs/benefits resulting[...]
It refers to the opportunity costs/benefits resulting from an accelerated deployment for IMs, operators[...]
20/08/2018
Answered
9
The fourth bullet mentions “infrastructure investments”. Can you please confirm that these investments[...]
Broadly yes, though there may be other participants in investments on certain infrastructures e.g. infrastructure[...]
20/08/2018
Answered
8
Since the railway lines comprising the Core Network Corridors and the Rail Freight Corridors are in some[...]
As outlined in Section 2.3 a task of the study is to select and determine 3 networks focussed on Core[...]
20/08/2018
Answered
7
In order to continue to stage 3 “Tender data”, the following attachments are requested: - Legal and regulatory[...]
Q1: What are the requirements to prove the legal and regulatory capacity? Legal and regulatory capacity[...]
09/08/2018
Answered
6
Please confirm if in “Tender Data”, all the parts of the proposal (A-F) have to be included in separate[...]
Part E: Financial offer, must be in a separated file from the other parts. The part A to D and F could[...]
03/08/2018
Answered
5
According to tender documents, Part C shall cover the elements included in section 4.2 Selection criteria[...]
It is acceptable to make reference to Part B.
03/08/2018
Answered