Results per page: 10 | 25 | 50 10 Questions found, displaying all Questions .
# Question Answer Last publication date Status
10
Is the assumption correct that it is allowed to submit a reference project per core competency (as indicated [...]
Yes, it is correct. It is allowed to submit different project reference for each core competency, however [...]
14/08/2018
9
The Tenderer understands that a framework contract will be concluded with the winning bidder, whereby [...]
Maximum amount 240 000 EUR for this Framework contract is based on the available budget and the previous [...]
14/08/2018
8
Is de aanname juist dat Evidence T2 abusievelijk is blijven staan? Zo nee, kan aanbestedende dienst motiveren [...]
Evidence T2 is linked with the Criterion T1. Due to the complex type of the works, contracting authority [...]
14/08/2018
7
What will be the deadline given by the contracting authority to submit the documentary evidence?
Contracting authority usually gives 3 working days deadline to submit the documentary evidence.
13/08/2018
6
Is de aanname juist dat indien de rechtsvorm van inschrijver een VOF is, inschrijver het legal entity [...]
Ja, de inschrijver moet het formulier "juridische entiteit voor privaatrechtelijke rechtspersoon" indienen [...]
13/08/2018
5
Is the assumption correct that for the financial offer it is sufficient to submit the excel file as included [...]
For the financial offer the Annex II - price tables (A, B, C) must be filled in. The comments / explanations [...]
13/08/2018
4
Is the assumption correct that if the legal enitity of the tenderer is a general partnership, the tenderer [...]
Yes, it is correct.
13/08/2018
3
unfortunately the cell "comments" of the table of the first sheet of Excel file (price list) is protected [...]
Thank you for your note. The corrigendum of the price table excel file is uploaded.
26/07/2018
2
The JRC sends a cutting plan and a sample drawing to the contractor for calculating the required amount [...]
C scenario is an example of one typical order and is independent of any drawing. In the C scenario we [...]
24/07/2018
1
how many items for each sample do you need?
The details of the scope and amount of samples is not yet defined. Please note that this is a Framework [...]
24/07/2018