64
|
Based on QA 38, is there a) a minimum and b) a maximum acceptable value for the breakdown components [...]
|
There is no minimum or maximum value for the associated percentage per component of the uplift percentage [...]
|
19/10/2018
|
|
63
|
Given the fact that contractors are only required to specify a single number that defines their financial [...]
|
The tenderers that submit identical financial offers will receive the same score. Please be reminded [...]
|
19/10/2018
|
|
62
|
For the second sub-question of this award criteria, you say that it is not required to provide a report [...]
|
We confirm that if you cannot provide an empty template due to technical reasons, it is acceptable if [...]
|
19/10/2018
|
|
61
|
Have we understood correctly that we need to provide the Annex A.1, Financial Analysis Form, with information [...]
|
Please refer to section 2.6.2. of the Invitation to tender. In the situation specified in the aforementioned [...]
|
19/10/2018
|
|
60
|
In the document Invitation to Tender, there is the following statement: “ If the tenderer intends to [...]
|
The use of freelancers for this contract is considered subcontracting. If freelancers will be used, the [...]
|
19/10/2018
|
|
59
|
With reference to “EN-Annex C_Financial tender form”. We understand that the Gross Hourly Rate is already [...]
|
Please see answer to Question40.
|
19/10/2018
|
|
58
|
With reference to “EN-Annex C_Financial tender form”. Could you please clarify the following? • We understand [...]
|
Regarding the first question, please see answer to Question44. Regarding the second and third questions [...]
|
19/10/2018
|
|
57
|
In case that we intend to use the CV of a freelancer, our understanding is that a letter of intent is [...]
|
Only a CV should be provided. A letter of intent is not required.
|
19/10/2018
|
|
56
|
With regards to the “Methodology Expert” profile description in the Technical Annex to SR2018/EXAMPLE [...]
|
The demonstrated experience of the methodology expert must be related to a project (or tasks within a [...]
|
18/10/2018
|
|
55
|
With reference to “EN-Annex B_Technical Tender Form” and the “Required Information related to Profile [...]
|
Please see answer to Question21. The total number of CV’s required is 5.
|
18/10/2018
|
|