41
|
In Annex 9.1, the "Project Reference" template, the service provider is asked to provide contact details [...]
|
Contact details refer to the client’s contact person. Please also see answer to question #19.
|
08/03/2019
|
|
40
|
In Annex 4, part 7.4.2.1.2 Proposed pool of key experts a certain number of key experts for the categories [...]
|
In the case where a tenderer has submitted more than the minimum number of Key experts, only the first [...]
|
08/03/2019
|
|
39
|
In Annex 7, the "Professional Profile Template", the service provider is asked to fill the field "profile [...]
|
In the section 'proposed role' tenderers shall indicate if its staff member would act as Framework Manager [...]
|
08/03/2019
|
|
38
|
In Annex 7, the "Professional Profile Template", the service provider is asked to provide the information [...]
|
Your understanding is correct.
|
08/03/2019
|
|
37
|
In the technical description for lot 1 (Appendix 1 of Annex 4) it is stated that "The service provider [...]
|
The example given by you can be a part of activities required (but not limited to) from the service provider [...]
|
08/03/2019
|
|
36
|
With regards to Change Management services in lot 2: what is the kind of assignments that can be expected [...]
|
The assignments will be related to the areas outlined in the LOT2 TECHINICAL DESCRIPTION. The activities [...]
|
08/03/2019
|
|
35
|
Can we include the profiles of both the Framework Manager and the Technical Expert as experts in the [...]
|
Yes, providing their profiles fit in the correct category.
|
08/03/2019
|
|
34
|
The tenderer is a member of a network of professional services firms. If the tenderer presents a reference [...]
|
With regard to criteria relating to the technical and professional ability, a tenderer may rely on the [...]
|
08/03/2019
|
|
33
|
Can we present a project references for both Lots if the services delivered during the project cover [...]
|
Yes, this is possible if the reference is relevant for both lots.
|
08/03/2019
|
|
32
|
Can the same expert be proposed for both Lot1 and Lot2 if he has relevant experience for both Lots?
|
Yes, the same expert can be proposed for both lots.
|
08/03/2019
|
|
31
|
In Appendid I: Lots detailed description it is stated for Lot No. 1 that the service provider will also [...]
|
The future service provider will be requested to perform organisational assessments on EIB’s strength [...]
|
08/03/2019
|
|
30
|
Section 7.3.2. Technical and professional capacity for all lots, of the ToR states: "The minimum amount [...]
|
No, as the requirement states ‘completed’. Except in cases of very large projects, if one or more phases [...]
|
08/03/2019
|
|
29
|
Dear, what is meant by total in annex 9 regarding project references? Is this about the total amount [...]
|
Please state in ‘total’ the value of the project in EUR.
|
08/03/2019
|
|
28
|
In the technical description for lot 2 (Appendix 1 of Annex 4) it is stated that the "service support [...]
|
The future service provider can propose project management activities based on “Lean” business methodology [...]
|
08/03/2019
|
|
27
|
We assume that the five topics "Strategic dialogue, knowlege sharing, process and procedures, collaboration [...]
|
Yes, your understanding is correct.
|
08/03/2019
|
|
26
|
Chapter 7.3.2. of Annex 4 states that a minimum number of 5 (five) contracts (project references) are [...]
|
In the case where a tenderer has submitted more than the minimum number of client references for the [...]
|
08/03/2019
|
|
25
|
After having examined the Financial Proposal Form, we assume that we only display Maximum Daily Rates [...]
|
Your understanding is correct.
|
08/03/2019
|
|
24
|
In Article 8 "Terms of payment" of the GTC it is stated, that unless otherwise agreed between the Bank [...]
|
Please note that Article 8 of the General Terms and Conditions describes EIB’s default payment conditions [...]
|
08/03/2019
|
|
23
|
“§6, i) of the General terms and conditions obliges the Service Provider to provide, at the Bank’s request [...]
|
This provision of the EIB’s General Terms and Conditions will be implemented by using the form ‘background [...]
|
08/03/2019
|
|
22
|
Do Profile 1, 2, ...refer to the actually proposed experts or to the category level by experience? Is [...]
|
Please state in ‘total’ the value of the project in EUR.
|
08/03/2019
|
|
21
|
In the last page of the TORs, a background check is requested. The table leaves space for two persons [...]
|
This document is meant to be signed by consultants who work 'intra-muros' EIB premises and/or have access [...]
|
08/03/2019
|
|
20
|
Our company has existed since 2005. With effect from Jan 2017, we have changed the form of our legal [...]
|
If the transformation from the GbR to GmbH was done by way of universal succession (i.e. the latter stepped [...]
|
08/03/2019
|
|
19
|
Annex 9.1 requires contacts for previous projects carried out. We believe that under the new General [...]
|
Yes, that would be sufficient.
|
08/03/2019
|
|
18
|
Under the contract, will only services provided at the premises of the EIB be remunerated or will home [...]
|
Both, services rendered at EIB premises as well as services provided from the provider’s office will [...]
|
08/03/2019
|
|
17
|
Can we use graphics, tables in the 50 page technical file?
|
Yes it is possible.
|
08/03/2019
|
|