70
Within the document it is not clear whether the insurance coverage required in paragraph 9.2 (377) - [...]
Article II.6.2. of the draft contract recites as follows: ' If required by the relevant applicable legislation [...]
04/07/2019
71
Within the document it is not clear the insurance coverage required in paragraph 9.2 (377) - Financial [...]
Please, see the answer under Question nr.70.
04/07/2019
16
With respect to tender compliance described in Annex 1, Part 1, section 2.4, can the JRC clarify whether [...]
The maximum total contract value is as described in point 2.6 in the Administrative Annex. Thus, price [...]
19/06/2019
94
With reference to the Service Contract draft, section II.13.1 "The Union acquires irrevocably worldwide [...]
The definition of "result" in section II.1. of the Service Contract draft refers to "any intended outcome [...]
30/07/2019
95
With reference to the Service Contract draft, section II.13.1 "The Union acquires irrevocably worldwide [...]
Please see the answer under question nr. 94.
30/07/2019
88
With reference to the Service Contract draft, does section II.18 'Termination of the Contract' stops [...]
Instead of 'Termination by either party is not applicable to this contract' please read: 'Article I.11 [...]
16/07/2019
50
With reference to the expiry date of the tender JRC/IPR/2019/OP/0365, scheduled for 04/07/2019, we would [...]
An OJ EU corrigendum will be published soon.
20/06/2019
59
With reference to the expiry date of tender , scheduled for 04/07/2019, can the delivery date be extended [...]
Please refer to Question and Answer nr. 38.
26/06/2019
81
With reference to chapter 5.4.4 - (251) of cellar_9a2fe08f-4580-11e9-a8ed-01aa75ed71a1.0005.02_DOC_4. [...]
Yes, it is possible to use data hashing but this shall be of type SHA256 for RCA, EA or AA because of [...]
15/07/2019
67
Will you be able to answer the questions we raised? Will internal CAs clients contract with the JRC or [...]
Refer to Questions and related Answers numbered 62 and 63.
28/06/2019
47
Will the JRC provide the possible fees that the stakeholders are willing to pay as an input for the business-model [...]
The JRC cannot guarantee that such input data on possible fees that are accepted by stakeholders will [...]
20/06/2019
63
Will internal CAs clients contract with the JRC or the contractor?
The JRC as contracting authority of this tender will only have a contractual relationship with the selected [...]
28/06/2019
62
Will external CAs providers contract with the JRC or the the contractor?
The JRC as contracting authority of this tender will only have a contractual relationship with the contractor [...]
28/06/2019
75
Which accredited certification bodies should we refer to in response to the competition? Those specified [...]
While the question remains not fully clear as no specific section of the tender documents is listed as [...]
09/07/2019
60
Where I find this document 'The tender report'?
As indicated in the invitation letter, the tender report is a document generated by e-Submission listing [...]
26/06/2019
2
When are the remaining documents going to be available for download?
The tender documents will be published as soon as possible. The deadline for submission of tenders will [...]
19/06/2019
78
We would understand if is possible to use VPN to have a management dedicated network to reach the safe [...]
The management of a dedicated network should be limited and confined to the respective environment only [...]
09/07/2019
17
We would like to understand the measurement of ""each day of delay"". a) We interprete a day of delay [...]
a) The WKP1 shall be performed within 12 (twelve) months starting from the date on which the contract [...]
19/06/2019
33
We interpret that the repository shall be developed from the scratch - is that assumption correct or [...]
The EU Root CA repository must be created from the scratch on the basis of the specifications of [1].
20/06/2019
89
We have reviewed the Service Contract, and would like to understand whether the draft Service Contract [...]
This is an open procedure, where any economic operator who is interested may submit a tender. This procedure [...]
18/07/2019
15
We can not find any requirements for a Service Level Agreement. Could you please indicate what availability [...]
The delivery of the deliverables shall be according to the time plan. In terms of operational availability [...]
19/06/2019
55
We assume the requirement is about keeping the anonymity of End-Entities. Do you agree that separation [...]
The requirement is not limited to the anonymity of End-Entities but it is related to the treatment in [...]
24/06/2019
61
Today, I received an email indicating that the tender responses are due in one week. I have seen numerous [...]
See OJ EU notice corrigendum, number 2019/S 123-299318 .
28/06/2019
93
The tender technical specifications refers to ETSI TS 102 941 intelligent Transport Systems (ITS), Security [...]
Similar to Question and Answer nr. 66. ETSI TS 102 941 v1.2.1 applies for the purpose of this tender [...]
26/07/2019
66
The Technical Specifications (Annex I to the Contract, Part 2) includes ETSI TS 102 042 version 2.4.1 [...]
ETSI TS 102 042 applies for the purpose of this tender since it is listed in Annex 3 of delegated regulation [...]
28/06/2019
26
The number of Authorisation Tickets (Certificates) is an important value for the performance requirement [...]
We cannot confirm nor correct your calculation. The rules to define the number of authorization tickets [...]
20/06/2019
25
The amount of Operation Meetings has been specified for Phase 1 (WPK2 and WPK3). It is however not clear [...]
The Operation Meetings are not specified for Phase 2, i.e. they are not foreseen. In case they should [...]
20/06/2019
44
Since there is no maximum of AT's defined in the tender - would you accept an offer defining a maximum [...]
No, we ask the potential contractor to give an indication on the cost for “Price for support for C-ITS [...]
20/06/2019
52
Si chiede di confermare che, in caso di subappalto: - non è richiesta l'indicazione della terna dei subappaltatori [...]
Si chiede costesemente di leggere il documento Allegato I – Parte 1 Allegato amministrativo per ulteriori [...]
20/06/2019
51
Si chiede di confermare che è ammessa la partecipazione in R.T.I. anche se non ancora costituito. A tale [...]
Si conferma che un'offerta può essere presentata da un raggruppamento di operatori economici. Si chiede [...]
20/06/2019
32
Shall the re-keying for Root CA/EA/AA executed automatically or triggered by an administrator?
It should be triggered by an administrator.
20/06/2019
83
Secondo l'ultimo voto del Parlamento dell'Unione Europea del 4 luglio sull'adozione della tecnologia [...]
Si prega di fare riferimento all'allegato I - Parte 2: Specifiche tecniche, pagina 29 [1] e [2] che specificano [...]
15/07/2019
85
Se è possibile la partecipazione diretta da parte della 'Stabile Organizzazione' italiana, è possibile [...]
Rimandiamo alla lettura della risposta alla domanda numero 84.
16/07/2019
9
Regarding tender specifications, Annex 1, Part 1, can the JRC confirm that for purposes of this proposal [...]
We confirm that the GPA agreement applies. The full text of the GPA and its appendices per country, as [...]
19/06/2019
19
Questions asked again, this time in layman's terms. Please respond accordingly. a) Can a solution be [...]
Ad a) Regarding the question on location of data centres, please see again the answer to Question 10. [...]
19/06/2019
84
Può la 'Stabile Organizzazione' italiana partecipare al tender (se in possesso dei requisiti richiesti [...]
Rimandiamo alla lettura dell'Allegato I – Parte 1 Allegato amministrativo, punto I.3. Modalità con cui [...]
16/07/2019
56
Please specifiy the minimum validity period of an AT that a C-ITS station could require. This is an important [...]
As already stated in answer #39 the contracting authority is not going to specify the minimum validity [...]
24/06/2019
7
Please note that the tendering documents are missing
The tender documents will be published as soon as possible. The deadline for submission of tenders will [...]
19/06/2019
10
Notwithstanding the JRC's draft Contract Section I.9.2 as it pertains to contractor processing of personal [...]
Regarding the question on territory of data processing, please refer to Annex I - Part 2 Technical Specifications [...]
19/06/2019
46
Let's assume a price X per C-ITS stations based on the support of 2.000.000 C-ITS stations. What will [...]
In Phase II Specific contracts will be issued by the Commission with specific requirements on the number [...]
20/06/2019
42
Is there any preference for the language of the offer (e.g. English)?
The preferred language to submit an offer is English.
20/06/2019
79
Is possible to specify the covering time of the insurance requested to cover all the services related [...]
The duration of the insurance should cover the operational duties related to root CA, EA, AA and the [...]
11/07/2019
64
Is possible to clarify: a) There shall be no way, either direct or indirect, to access any other environment [...]
The details on the communication requirements between disaster and recovery environment are to be detailed [...]
28/06/2019
73
Is not clear in the tender documentation the replica synchronization mode between Production and DR environment [...]
The answer is asynchronous, as the environments shall remain fully separated during normal operation. [...]
09/07/2019
41
Is it necessary to possess the ISO 27005 certification at project start or can it be obtained during [...]
The key point regarding ISO 27005 certification/compliance is that the EU Root CA, EA and AA must pass [...]
20/06/2019
14
Is it correct to assume that the external EA or AA must satisfy the Certificate Policy (CP) requirements [...]
No, we do not consider that a correct assumption. The contractor will have to define the EU root CA’s [...]
19/06/2019
87
In the Evaluation table row 25, could you please indicate which costs should the provider insert?
The base service provisions include the costs for the support for the EU Root CA, internal EA and AA [...]
16/07/2019
80
In the EN-04 Financial offer Evaluation table, more exactly in the row 25, Base services provision, is [...]
The second phase of the contract is regulated by a framework contract, and services will be ordered by [...]
11/07/2019
6
In the Document Library only the Invitation letter is available, do you expect to upload the Tender specifications [...]
The tender documents will be published as soon as possible. The deadline for submission of tenders will [...]
19/06/2019
23
In terms of "interacting with the Accredited Auditors" can the JRC clarify whether CA compliance audits [...]
We confirm that the contractor will be responsible for the entire process of auditing the EU Root CA, [...]
20/06/2019