The Commission has already offered the provision of internal translation services for commission related [...]
|
The tender specifications of this call procedure cannot be modified.
|
16/09/2019
|
|
24
|
The answers to Questions 22 and 23 are not clear to us. We kindly request a final clarification: Currently [...]
|
The following generic courses are already available: 1) Introduction to UCPM, 2) Information Management [...]
|
13/09/2019
|
|
23
|
The answer to question #15 states that the existing generic courses have to be translated into five other [...]
|
The bidder is expected to translate the 3 already existing online lectures (UCPM introduction - Cultural [...]
|
12/09/2019
|
|
22
|
In the technical specifications it is stated under "Task 5: Designing", that three additional online [...]
|
The bidder is expected to translate both the 3 existing online lectures and the 3 additional online lectures [...]
|
12/09/2019
|
|
21
|
Is an Identification of the Tenderer attached as an appendix necessary, regardless singel or joint tenderer [...]
|
Please note that the document for the identification of the tenderer as requested in previous calls for [...]
|
29/08/2019
|
|
20
|
Could you please indicate to which postal address both documents should be be sent. Thank you
|
Please send original documents to : EUROPEAN COMMISSION Directorate-General for European Civil Protection [...]
|
29/08/2019
|
|
19
|
Dear Madam / Sir, Does the answer to Question 10 (given on 01/08/2019) “Course visits / peer reviews [...]
|
Question 10 only applies to Lot 1-7. For lot 8, course visits may be organised to other lots to ensure [...]
|
26/08/2019
|
|
18
|
On page 6 it is written that "technical offer shall be of maximum of 30 pages (A4, font 12)". Does this [...]
|
This rule of 30 pages applies to all lots. Curriculum can be attached as an annex to the technical offer [...]
|
26/08/2019
|
|
17
|
Is it correct that the maximum submitted pages of the technical proposal is 30 pages excluding appendices [...]
|
It is correct that the maximum number of pages for the technical proposal is 30. However, there is no [...]
|
26/08/2019
|
|
16
|
Within 2.3/2.3.1 Requirements under Task 1 (page 13) it is written that "contractor shall participate [...]
|
It is expected that the core team as described in section 2.3.1 participate in the kick-off meeting. [...]
|