Call for tenders' details

Title:
Management of the European Citizens’ Initiative Online Collaborative Platform
Contracting authority:
Secretariat General (SG)
TED publication date:
05/08/2019
Time limit for receipt of tenders:
24/09/2019
Status:
Closed
Show filter parameters

Results per page: 10 | 25 | 50 6 Questions found, displaying all Questions .
# Question Answer Last publication date Status
6
In case of a sole tenderer, should subcontractors provide a statement of the average annual manpower [...]
The criterion applies to the tenderer as a whole which means assessing the capacity of the tenderer together [...]
03/09/2019
5
Regarding Criterion F2, if we meet two of the ratios but not all of them, are we still eligible to submit [...]
Not meeting all of the ratio's does not prevent you from submitting an offer.
23/08/2019
4
Which information should be indicated in the statement on the average annual manpower and the number [...]
The number of staff (full time, part time, full time equivalent) should be provided for each of the last [...]
23/08/2019
3
What is the meaning of “Capacity: average annual project costs/own funds <0.5”?
The average annual project cost is based on the total price of the contract according to the offer and [...]
20/08/2019
2
Regarding the Criterion T2 – are only service contracts’ projects eligible as evidence or projects funded [...]
Criterion T2 refers to projects in general and not service contracts specifically. References to projects [...]
20/08/2019
1
The specifications ask for copies of the profit and loss accounts and balance sheets. Provided that according [...]
Yes it would be sufficient to upload the audited annual accounts -
20/08/2019