17
|
If the work within the field(s) of experience has already been finished, but the overall project work [...]
|
References may not include ongoing projects. However, you can provide evidence that the work in question [...]
|
17/09/2019
|
|
16
|
Can the project value be accounted for all services provided within a large project?
|
Provided that we understood your question correctly, please note that regardless of the amount of your [...]
|
17/09/2019
|
|
15
|
Please be aware that after the UK's withdrawal from the EU, the rules of access to EU procurement procedures [...]
|
The clause does not apply to subcontractors. Economic operators may choose the subcontractors they like [...]
|
16/09/2019
|
|
14
|
It is stated that the contractor will provide assistance to public authorities, amongst other things, [...]
|
The tenderer can offer to assist public authorities with pilot tests, but can only perform services and [...]
|
16/09/2019
|
|
13
|
Is there a preference by the EU Commission in which timely manner the Tasks 1 and 2 should be executed [...]
|
The duration of the contract of 24 months will probably require parallel and independent execution of [...]
|
16/09/2019
|
|
12
|
Is it necessary to hand in CVs for a supporting expert team? Would a list of names and qualifications [...]
|
As stated in the tender specifications, the experience of the project team required under criterion B3 [...]
|
16/09/2019
|
|
11
|
Is it permissible that one reference project covers multiple fields of experience? In that case it would [...]
|
Yes.
|
16/09/2019
|
|
10
|
Is it meant, that for each field of experience at least three reference projects must be provided, resulting [...]
|
Indeed, for each of the three fields of experience the tenderer has to provide three reference projects [...]
|
16/09/2019
|
|
9
|
Is it permissible, by the regulations of the two projects (Lindanet, current tender ENV.D.1/ETU/2019/ [...]
|
A beneficiary funded by Interreg Europe in the context of LINDANET can receive assistance from the contractor [...]
|
16/09/2019
|
|
8
|
Based on the dynamic environment of the projects and many stakeholders involved, it is foreseeable that [...]
|
In the offer, the tenderer should respect the foreseen maximum duration of 24 months and plan the activities [...]
|
16/09/2019
|
|
7
|
The project tasks 1 and 2 need to be completed in 24 months. In a logical sequence, six sites that need [...]
|
Indeed, the duration of the contract of 24 months will probably require parallel and independent execution [...]
|
16/09/2019
|
|
6
|
Do sites with lindane production related contamination (dioxins, furanes) also need to be addressed?
|
Since the scope of the contract focuses on lindane and HCH, contamination with other substances should [...]
|
16/09/2019
|
|
5
|
Next to the lindane production sites, landfills and treatment centres there are sites on which HCH soil [...]
|
Although the scope of the contract focuses on production sites, waste deposits, landfills and treatment [...]
|
16/09/2019
|
|
4
|
The meetings with the Commission can be carried out by video-conference except for the first and final [...]
|
The physical meetings with the Commission will be organized in the building of DG Environment, Avenue [...]
|
16/09/2019
|
|
3
|
Tenderers are required to identify all subcontractors and provide an indication of the proportion of [...]
|
The tenderer should propose a number of projects/cases within the maximum budget that is available. If [...]
|
16/09/2019
|
|
2
|
We noticed that the submission deadline for questions is 20 September, with answers to questions provided [...]
|
The deadline for asking and answering questions is standard and cannot be extended. All other tenderers [...]
|
16/09/2019
|
|
1
|
We notice that the requirement of submitting the Letters of Interest (for at least six different projects [...]
|
The deadline for submission of the offers (one month after the summer holidays, more than two months [...]
|
16/09/2019
|
|