Call for tenders' details

Title:
Technical Assistance to Support Afreximbank in Lending to Trade Infrastructure a...
Contracting authority:
European Investment Bank (EIB)
TED publication date:
09/08/2019
Time limit for receipt of tenders:
20/09/2019
Status:
Closed
Show filter parameters

Results per page: 10 | 25 | 50 14 Questions found, displaying 1 to 10.[First/Prev] 1, 2 [Next/Last]
# Question Answer Last publication date Status
14
In Specific professional experience for Key expert 2 it is written: "Strong regional experience as demonstrated[...]
Please take into consideration the revised requirements on the updated version of the Terms of References[...]
10/09/2019
13
Dear Sir/ Madam, We would like to address the following clarification question for the current tender[...]
According to the provisions of the ToR, point 6.1.1 the team of experts, as a whole, should be fluent[...]
10/09/2019
12
In the ToR, page 14, it is written that „the number of on field missions is expected not to be more than[...]
The individual experts are expected to carry out their work at the HQ of Afreximbank in Cairo. Three [...]
10/09/2019
11
Considering the description of Component 4 (ToR, page 9) and the description of the respective target[...]
Component 4 targets capacity building of the final beneficiaries (client borrowers) of Afreximbank and[...]
10/09/2019
10
The concept of "bankable projects in ..." (ToR, page 10, Item 4.2.1, sub i) considers the development[...]
The concept of bankable projects in 4.2.1. refers to SME projects also based in industrial parks/export[...]
10/09/2019
9
Eligible projects should comply with EIB's policies and procedures, however the TOR does not specifies[...]
The selection of projects to be financed by Afreximbank must fulfil Afreximbank’s project appraisal approach[...]
10/09/2019
8
In (a) it is written: "The tenderer … has implemented, during the last 5 years … at least 2 project(s[...]
A maximum number of 5 project references can be submitted.
10/09/2019
7
In b) it is written: " … Each CV should be no longer than 3 pages and only one CV must be provided for[...]
Please see answer to Question3
10/09/2019
6
On page 17, it is written: "Non-key experts / short term experts (minimum 330 working days)". On page[...]
Please see answer to Question1
10/09/2019
5
Page 5 of the Instruction to Tenderers states: “b) … the CVs of each of the key experts. Each CV should[...]
Please see answer to Question3
10/09/2019