Call for tenders' details

Title:
Assessment of climate action in the programmes prepared by the Member States for...
Contracting authority:
European Commission, DG for Climate Action (CLIMA)
TED publication date:
13/08/2019
Time limit for receipt of tenders:
04/10/2019
Status:
Closed
Show filter parameters

Results per page: 10 | 25 | 50 10 Questions found, displaying all Questions .
# Question Answer Last publication date Status
10
We kindly ask you to confirm that the financial proposal should, together with other items, include the [...]
The financial proposal and the contract shall be based on the assessment of 287 programmes, which is [...]
24/09/2019
9
Is budget of 1.000.000 € referred to total project budget or only to the proportion carried out by the [...]
The tenderer’s share of each project should be at least €1.000.000, i.e. (1) if the tenderer is the lead [...]
23/09/2019
8
If subcontractors are not entered on e-submission via a PIC number, and only listed in the technical [...]
You must name the subcontractor(s) and identify them by an e-mail address, VAT No, ID card etc. You are [...]
20/09/2019
7
Should both programme funding ERDF and CF be covered with provided references?
Experience with both funds is required as per Criterion A1 and the tenderer must therefore provide references [...]
16/09/2019
6
Referring to the Tender Specifications for Lot 1, 2.3.4.b., Criterion B4: ‘Collectively the team of experts [...]
We confirm that this includes Maltese and Gaelic in the 24 official languages.
29/08/2019
5
Dear Madame/Sir, in relation to Lot 1 of the above mentioned procedure, according to what specifies section [...]
The reference periods are correct as specified under each specific Evidence (i.e. 5 years for Evidence [...]
29/08/2019
4
Evidence 1 is to be interpreted as: (first option) each of the two projects, requested as reference, [...]
The two projects required as Evidence A1 can have the same or a different combination of the areas listed [...]
28/08/2019
3
For lot 1, Evidence A1 require at least two projects of at least 1.000.000 EUR in the last 5 years meeting [...]
The two projects required as Evidence A1 can have the same or a different combination of the areas listed [...]
28/08/2019
2
Is our interpretation correct that evidence can be brought in the form of two projects in the last five [...]
The two projects required as Evidence A1 can have the same or a different combination of the areas listed [...]
28/08/2019
1
Do the two references required under Criterion A1 have to relate to projects which each concern both [...]
The two projects required as Evidence A1 can have the same or a different combination of the areas listed [...]
27/08/2019