# Vprašanje Odgovor Zadnja objava Status
27
In order to tell the transportation company that will bring the letter; would it be possible to get a [...]
See following: Postal address: European Commission DG CONNECT R2 – Budget & Finance BU25 04/115 Jaana [...]
04/11/2019
26
Would it be acceptable for the EU to have 2 subcontractors which annexes 4 and 6a are loaded without [...]
Please request subcontractors to sign the documents and provide them by e-mail. There is no possibility [...]
29/10/2019
25
on the e-submission guide it is said : "If you consider the tender complete and ready for submission, [...]
It has to be person(s) authorised legally representing the company (same person who has signed the Annex [...]
29/10/2019
24
Could you please let us know if a recent trade register excerpt is accepted as Notice of appointment [...]
If the name of the legal representative is clearly mentioned in the notice of an appointment, this document [...]
28/10/2019
23
Criterion B10 requires: "Collectively the team of at least 10 people should have knowledge of the EU [...]
For each EU Member State having signed the EU QCI, in the team suggested for carrying out the tasks there [...]
28/10/2019
22
Can you please tell us if it is required to provide the below inputs at the submission stage: “The Contractor [...]
It is not needed at the submission stage. The aspects linked to the SAL (security aspect letter) will [...]
28/10/2019
21
Is it necessary to provide evidence of the compliance with “environmental, social and labour law……Directive [...]
This is included in the Annex IV: Declaration of honour. No additional documentation needed.
28/10/2019
20
The tender specifications say that subcontractors must complete Annex 4 if (1) their share of the contract [...]
We confirm that it is all selection criteria's listed under sections 4.2.2, 4.2.3 and 4.2.4 in the tender [...]
23/10/2019
19
Can you confirm the evidence described in Chapter VI of the Annex 4 at the top of the page 39 (a recent [...]
This is required only from the tenderer for whom the contract is awarded.
23/10/2019
18
Chapter VII of Annex 4 requests the tenderer to declare they comply to the selection criteria applicable [...]
The filling of the Annex IV is done individually per economical operator participating to the call declaring [...]
23/10/2019
17
In annex 5, Can you confirm that, in the following sentence: “1) To submit a tender as a partner in the [...]
The group of partners relates only to the tenderers and not subcontractors. Since we have no access to [...]
23/10/2019
16
Where exactly should the tender include the proportion of the contract that will be subcontracted? In [...]
Financial tender would probably be the best place for it.
23/10/2019
15
Should we receive some documents concerning footnote 2 and 3 in the SAL “Reference will be provided as [...]
The security aspect letter is provided at this stage as an example only. The official version including [...]
23/10/2019
14
In the context of subcontractors, could you please specify what you mean with "whose capacity is necessary [...]
The declaration of honour Annex IV has to be provided by subcontractors whose capacity is needed to fulfil [...]
23/10/2019
13
Do members of an external consultancy board not involved in the execution of the tasks have to sign Annex [...]
If the contribution of an external consultancy board is financed by the contract resulting from this [...]
22/10/2019
12
Could you please let us know which member of the subcontracting company has to sign Annex 6a: an authorised [...]
The letter of intent for subcontractor should be signed by person legally authorised to represent the [...]
22/10/2019
11
Could you please tell us if the requested photocopy of the notice of appointment of the persons authorised [...]
The document can be provided in the national language of the partner/subcontractor, but of course if [...]
21/10/2019
10
Can a subcontractor whose competences are not necessary to fulfil the selection criteria act as Work [...]
The tender specifications do not refer to work packages, hence the question on work package leaders is [...]
21/10/2019
9
Annex 6a states: […] Declares hereby that, in case the contract is awarded to [name of the tenderer], [...]
The name of the tenderer in Annex 6a should contain the names of all partners participating in the tender [...]
18/10/2019
8
Shall identified subcontractors who have to sign Annex 4 also sign Annex 3 (admin. ID form) ?
The subcontractors do not need to sign Annex 3. In accordance with the Checklist of documents to be submitted [...]
18/10/2019
7
Would it be possible to obtain an extension of the due date for submission to Friday November 14th?
Unfortunately, it is not possible to extend the deadline.
18/10/2019
6
For selection criteria A3, A4, B10, could you please provide clarification on the conditions for the [...]
For technical selection criteria the evidence needs to be provided with the offer. See the annex for [...]
16/10/2019
5
On page 18 of tender specifications, we read “In case of subcontracting, all subcontractors whose share [...]
I confirmt that tenderers are required to identify all subcontractors whose share of the contract is [...]
15/10/2019
4
We assume that Horizon 2020 rules do apply and that Swiss entities are fully eligible to apply. However [...]
The Horizon 2020 participation rules relates to grants not procurement. Only bi/pluri-lateral treaties [...]
11/10/2019
3
1) Can the same partner ( or subcontractor) be part of more than one consortium for the bid? 2) Can it [...]
1) Yes. Economic operators are free to organise themselves as they so wish, i.e. they can submit a tender [...]
09/10/2019