Results per page: 10 | 25 | 50 42 Questions found, displaying 1 to 10.[First/Prev] 1, 2, 3, 4, 5 [Next/Last]
# Question Answer Last publication date Status
31
In section 4.2.4.1.1 of the technical specifications is stated "... the composition of the family to [...]
"Other source" within this context means any source which could provide necessary information. For example[...]
23/09/2014
42
Are there cases in which law undergoes modifications, although these are not explicitly mentioned in [...]
As a rule only explicitly mentioned modifications have to be consolidated. However, in case of any doubts[...]
22/09/2014
41
The specifications of the call for tender do not include the Backlog production. Could you please confirm[...]
As stated e.g. in point 4.2.1 of the tender specifications, the contract includes both daily consolidation[...]
22/09/2014
40
Does the tenderer understands correctly, that taking into account the estimated value of the contract[...]
Your understanding is not correct. The minimum level of turnover for one year is: - for LOT 1: 2,083,333.33[...]
19/09/2014
39
Technical annex A2 (CONSLIFE system) : rejection of delivered files. The described procedures (ACK/NACK[...]
'ACK/NACK' messages as described in points 4.4 and 4.5 are in fact ONLY applied for manual validation[...]
19/09/2014
38
In Article I.4.1 of the contract of LOT 1 is stated “The second contractor in the order of the cascade[...]
Should it happen that the contract is terminated with the first contractor, the second contractor will[...]
18/09/2014
37
Could you please confirm that only for Lot 2 the PARFs have to be accompanied by a Reference letter?
Your understanding is not correct. For both lots PARFs have to be accompanied by a Reference letter.
17/09/2014
36
We refer to point 4.4 of the Specifications - e-Prior. It is foreseen to use in future the electronic[...]
At this stage in is not possible provide any further information about the use and the impact of e-Prior[...]
17/09/2014
35
Additionally, the tenderer understands that the supporting evidence of legal, economic, financial and[...]
Yes, your understanding is correct.
17/09/2014
34
As indicated in the tender specification (Invitation letter, point 3) the tender must be prepared in [...]
The tender will not be rejected if Section Four is submitted in an official language of the EU other [...]
17/09/2014