21
|
The short deadline of the procurement procedure provides a clear advantage to those parties who did the [...]
|
Dear Madam, Dear Sir, Extending the deadline is, unfortunately, not an option. Regarding equal conditions [...]
|
18/10/2019
|
|
20
|
Page 25 of the tender specifications reads “As results are likely to be made available to the public [...]
|
Dear Madam, Dear Sir, As mentioned in the text you quoted, the technical solution proposed should not [...]
|
18/10/2019
|
|
19
|
In section 3.2.2 of the Technical Specifications, it is said that "The contractor, in cooperation with [...]
|
Dear Madam, Dear Sir, The number of sources is expected to be in tens, as you mention. The documents [...]
|
18/10/2019
|
|
18
|
Within the declaration of honour, section VII _ Selection Criteria, it says that evidences must be provided [...]
|
Dear Madam, Dear Sir, Your understanding is mostly correct. In the first stage, the submission of the [...]
|
18/10/2019
|
|
17
|
As concerns the identification of the tenderer, it is mentioned that the tenderer “must indicate the [...]
|
Dear Madam, Dear Sir, Your understanding is correct: by submitting the Legal Entity Form duly filled [...]
|
18/10/2019
|
|
16
|
11. According to section 1.10 of the tender specifications “the tenderer (and each member of the group [...]
|
Dear Madam, Dear Sir, Tenderers are expected to disclose such information (SME or not) either via the [...]
|
18/10/2019
|
|
15
|
Who is responsible for costs regarding deployment?
|
Dear Madam, Dear Sir, As described in section 3.6.4 of the tender specifications, the contractor will [...]
|
18/10/2019
|
|
14
|
Is there a large “golden standard” set available?
|
Dear Madam, Dear Sir, Unfortunately a large set of annotated documents that could form a 'golden standard [...]
|
18/10/2019
|
|
13
|
Do you require more quality parameters than just accuracy (Recall/precision)?
|
Dear Madam, Dear Sir, No, other quality parameters are not required.
|
18/10/2019
|
|
12
|
In the conclusion of the ULiege PoC document, a multi-lingual approach is listed as a future next step [...]
|
Dear Madam, Dear Sir, The required scope of the delivered solution in the call for tender is limited [...]
|
18/10/2019
|
|
11
|
“Editability of source documents”: Is the requirement a user-interface for annotating source documents [...]
|
Dear Madam, Dear Sir, Developing a user-interface allowing manual annotation of documents is not among [...]
|
18/10/2019
|
|
10
|
Feedback and the ability to “incorporate human expert feedback to maintain and continuously improve the [...]
|
Dear Madam, Dear Sir, Please check our previous answer to question n° 8, Question8.
|
18/10/2019
|
|
9
|
Can FISMA adopt the DG Digit data platform AWS cloud infrastructure for the present call for tenders? [...]
|
Dear Madam, Dear Sir, DG FISMA can accept DG DIGIT data platform, because it forms part of the contracting [...]
|
18/10/2019
|
|
8
|
The tender specifications refer to a “near 100% accuracy through human assisted ML”. In our experience [...]
|
Dear Madam, Dear Sir, Although achieving close to 100% accuracy is one of the objectives of the project [...]
|
18/10/2019
|
|
7
|
In order to put together a response, (...) contractor and its partners would require an extension of [...]
|
Dear Madam, Dear Sir, Unfortunately, it is not possible to extend the deadline for submitting the tender [...]
|
18/10/2019
|
|
6
|
Dear Sir/Madam, In point 3.2.2 2.b in the Tender Specification document such task is identified: "The [...]
|
Dear Madam, Dear Sir, The description of KOEL system is provided in the Annex 10 to the tender specifications [...]
|
17/10/2019
|
|
5
|
We note in the TOR the statement "As results are likely to be made available to the public and reusable [...]
|
Dear Madam, Dear Sir, In order to maximise reusability and further extensibility of the developed solution [...]
|
14/10/2019
|
|
4
|
With regard to the project experience of the contractor, would commercial contracts for private clients [...]
|
Dear Madam, Dear Sir, As specifically mentioned in section 2.3.3.(a) of the tender specifications, the [...]
|
11/10/2019
|
|
3
|
We note in Annex 10 the requirement to use Oracle for the database. To which extent would the Commission [...]
|
Dear Madam, Dear Sir, The aim of the call for tenders is to develop tools for integration in the environment [...]
|
11/10/2019
|
|
2
|
Would any maintenance of the tool after delivery of the contract be subject to a maintenance contract [...]
|
Dear Madam, Dear Sir, The contracting authority does not intend to enter into any maintenance contract [...]
|
11/10/2019
|
|
1
|
To which extent would the contractor be allowed to re-use knowledge acquired during the course of the [...]
|
Dear Madam, Dear Sir, Please consider the provisions of art. II.13.1 and, in particular, art. II.13.3 [...]
|
11/10/2019
|
|