47
|
Dear Sir, In the tender documentation the contract signature is scheduled for Q4 2019. The first specific [...]
|
You refer to point 6.2 of the Annex I. The indicative planning expressed therein should be postponed [...]
|
03/12/2019
|
|
46
|
On Section 4.5, the Authority specifies:” Each member of the consortium must provide the required evidences [...]
|
Sub-points 1 and 2: Assessment of compliance to the economic, financial, technical and professional capacity [...]
|
29/11/2019
|
|
45
|
In the recent update of the requirements for the gyro stabilized turret, Frontex requested the resolution [...]
|
The bidder has to fulfil all the mandatory requirements of the Terms of References / Tender Specifications [...]
|
28/11/2019
|
|
44
|
As per Tender Specifications (Annex I), the current tender is based on the previously assigned Trials [...]
|
The bidder has to fulfil all the mandatory requirements of the Terms of References / Tender Specifications [...]
|
28/11/2019
|
|
43
|
At present, there is no airworthiness certification standard for UAVs in our country, but our UAVs have [...]
|
The proposed platform must hold a valid certificate of airworthiness issued by the aviation safety regulator [...]
|
25/11/2019
|
|
42
|
Since the RPAS is classified as Military Equipment, it requires that the local end user entity will be [...]
|
Host national authority identity, for custom clearance purposes, will be made available at the moment [...]
|
25/11/2019
|
|
41
|
Paragraph 6.4.2/c of the Annex I requires that the maritime surveillance radar is designed for air to [...]
|
The bidder has to fulfil all the mandatory requirements of the Terms of References / Tender Specifications [...]
|
25/11/2019
|
|
40
|
Paragraph 6.4.2/c of the Annex I requires that the maritime surveillance radar is able to manage a minimum [...]
|
Paragraph 6.4.2/c of the Annex I requires that the maritime surveillance radar is able to manage a minimum [...]
|
25/11/2019
|
|
39
|
The 19th November you extended the deadline for Questions from 21.Nov to 05.Dec (the website is updated [...]
|
Recently Frontex has published one additional document on TED website, titled "correction of 19.11.2019 [...]
|
21/11/2019
|
|
38
|
Dear Sir / Madam, A recent update on the Question deadline specifies 05/12/19, while the deadline for [...]
|
Recently Frontex has published one additional document on TED website, titled "correction of 19.11.2019 [...]
|
21/11/2019
|
|
37
|
Are there any information about airports of this mission in three countries (Greece, Malta, Italy), such [...]
|
There is no more information regarding the airports of the mission in Greece, or Malta or Italy. No transfer [...]
|
19/11/2019
|
|
36
|
Is airworthiness certification required? As far as we know, there is no airworthiness certification standard [...]
|
The proposed platform must hold a valid certificate of airworthiness issued by the aviation safety regulator [...]
|
19/11/2019
|
|
35
|
"The asset is certified of operating in any class of airspace under VFR (Visual Flight Rules) and IFR [...]
|
The proposed platform must hold a valid certificate of airworthiness. This certificate shall be recognized [...]
|
19/11/2019
|
|
34
|
Before each flight mission, does the contractor need to go to ATC to apply for airspace? Waiting for [...]
|
The contractor has the exclusive responsibility to get ATC authorization in the FIRs relevant for this [...]
|
19/11/2019
|
|
33
|
With reference to Para 7.3.2, the sentence about creation of rules, included in the scoring criteria, [...]
|
Point 6.6.5.a describes the Compiled Operational Picture created in the Control Ground Station. The reference [...]
|
19/11/2019
|
|
32
|
With reference to Para 6.4.2, not all the information transmitted in the scenario of a RPAS mission can [...]
|
The statement "All the communication has to be encrypted." refers to the communications listed in item [...]
|
19/11/2019
|
|
31
|
With reference to Para 6.4.2, kindly provide an expected quantity of authorized IP addresses.
|
The expected quantity of authorized IP addresses is from 10 to 20.
|
19/11/2019
|
|
30
|
With reference to Para 6.4.2, please confirm that only the mission chief will have external access to [...]
|
Confirmed.
|
19/11/2019
|
|
29
|
With reference to para 6.4.2, please clarify the meaning of "administer locally". What will be the functions [...]
|
In case the host country or Frontex request to add new IP address for the distribution list and give [...]
|
19/11/2019
|
|
28
|
In the definition of MISB ST 0601, you mention that "The metadata enables advanced Full Motion Video [...]
|
Our data processing engine is able to accept full MISB data stream. The minimum metadata tags required [...]
|
19/11/2019
|
|
27
|
In the definition of MISB ST 0601, the tender specification mentions that the metadata enable "multicast [...]
|
The term “multicast broadcasting” from the definition section of the Annex I does not refer to IP multicast [...]
|
19/11/2019
|
|
26
|
Could you please confirm which are the specific eligibility requirements, if any, for the participation [...]
|
In order to fulfil the eligibility criteria, the Tenderer or in case of consortium all member of consortium [...]
|
19/11/2019
|
|
25
|
Further to the Informative Meeting, could you please confirm that security clearances are required for [...]
|
Only the staff involved in the data/information management should be security cleared. Separate security [...]
|
19/11/2019
|
|
24
|
Further to the information received during the Informative Meeting held in Warsaw on October 28th, can [...]
|
The duration of the missions will be stipulated based on the operational needs. The asset has to have [...]
|
19/11/2019
|
|
23
|
The partial fulfillment of a mandatory requirement is a cause of exclusion of the proposal?
|
The bidder has to fulfil all the mandatory requirements of the Annex I and Appendix 1.
|
19/11/2019
|
|
22
|
Could you please specify what type of certification is needed for the pilots while no certification is [...]
|
The pilots proposed in the tender shall have a valid license to operate the proposed RPAS issued by a [...]
|
19/11/2019
|
|
21
|
Could you please better specify the meaning of "all weather" while this definition doesn't exist in any [...]
|
The term ‘all weather’ shall be understood as the capacity to perform day/night flights and to take-off [...]
|
19/11/2019
|
|
20
|
As declared by Frontex during the information meeting held in Warsaw on October 28th, could you please [...]
|
The bidder has to declare in the offer that there is not any limitation for him to deliver operational [...]
|
19/11/2019
|
|
19
|
As declared by Frontex during the information meeting held in Warsaw on October 28th, could you please [...]
|
The duration of the missions will be stipulated based on the operational needs. The asset has to have [...]
|
19/11/2019
|
|
18
|
The operations will be scheduled 5 days a week or 7 days a week?
|
The flights will be scheduled based on the operational needs, but the service has to be available 24/ [...]
|
19/11/2019
|
|
17
|
In case all the competitors have at least one requirement not compliant with the mandatory ones, how [...]
|
The bidder has to fulfil all the mandatory requirements of the Annex I and Appendix 1.
|
19/11/2019
|
|
16
|
More than 30 mandatory are listed in In Table 1 of the Tender Specification while in the excel file " [...]
|
The bidder has to meet all the requirements of the Annex I – Tender Specifications. All the requirements [...]
|
19/11/2019
|
|
15
|
Could you provide an average price for the airport infrastructure rental in Italy, Greece and Malta? [...]
|
The bidder is responsible to take into consideration these prices based on its market research and experience [...]
|
19/11/2019
|
|
14
|
The cost for the utilization of the National Radio Frequencies Bands is in an important part of the service [...]
|
The bidder is responsible to take into consideration these prices based on its market research and experience [...]
|
19/11/2019
|
|
13
|
As the industry is fast growing and serious new entrants can show 3 Mio EUR turnover for 2019 but were [...]
|
Our requirements concerning turnover have already been defined in the quoted point 6.8.2 of the Annex [...]
|
14/11/2019
|
|
12
|
Would a solution providing all required payload elements under the weight of 235kg be acceptable for [...]
|
Payload and platform requirements are considered separately in this tender. RPA platform requirements [...]
|
09/11/2019
|
|
11
|
Our company has extensive experience and expertise in the provision of RPAS maritime configuration services [...]
|
The questioned requirement of evidence of 3 reference letters is not the first case of existence of such [...]
|
07/11/2019
|
|
10
|
Please confirm our understanding that the required technical proposal (referring to sections 6.4, 6.5 [...]
|
The bidder has to fulfil all the requirements referred to preparation of its complete technical offer [...]
|
07/11/2019
|
|
9
|
The required evidences entail 3 reference letters. Given the sensitivity of our services, and the fact [...]
|
The questioned requirement of evidence of 3 reference letters is not the first case of existence of such [...]
|
07/11/2019
|
|
8
|
Can you please confirm the meeting minute will be published by today CoB?
|
As stated in the Annex I - Tender Specifications, point 4.11, the list of questions and answers from [...]
|
06/11/2019
|
|
7
|
As per the tender notice, an informative meeting was to be planned. When is it to take place?
|
As specified in the Annex I – Tender Specifications, point 4.11, the informative meeting was organised [...]
|
06/11/2019
|
|
6
|
Tender Specifications, Section 5.1.2 – please advise what are the scenarios in which the contractors [...]
|
FWC in cascade apply a vertical ranking system. Where the 1st contractor is not capable or interested [...]
|
06/11/2019
|
|
5
|
Tender Specifications, Section 5.1.2 – we understand that the intent of Frontex is to sign a Framework [...]
|
Yes.
|
06/11/2019
|
|
4
|
Draft Contract Clause II.15 (Liquidated Damages) – the formula for calculating liquidated damages is [...]
|
Provisions of draft contract regarding any change in the General Conditions cannot be discussed, since [...]
|
06/11/2019
|
|
3
|
Tender Specifications, Annex I, page 23 – we assume that FRONTEX will define which RAW data will be at [...]
|
As stipulated in the Annex I - Tender Specifications, on page 23 - “The bidder is requested to describe [...]
|
06/11/2019
|
|
2
|
Good Morning, Thank's for answering my previous question and providing us with some time to prepare our [...]
|
Thank you for spotting our clerical error, which in fact has already been corrected. The new deadline [...]
|
05/11/2019
|
|
1
|
We are in the process of completing a competitive service offering for Frontex and would please require [...]
|
The deadline for submission of offers was extended to 29 November 2019. The relevant Corrigendum to the [...]
|
05/11/2019
|
|