# Kysymys Vastaus Julkaistu viimeksi Tila
25
We notice that there is a standard formulation that the project is free of taxes. It is our experience [...]
The Consultant might be exempt from direct and indirect taxes in the countries where it will have to [...]
04/11/2019
7
1) In the ITT, ‘3. Technical capacity of the tenderer’ the selection criteria mentions a reference period [...]
The reference period for the projects is 5 years. One original hardcopy and an electronic version should [...]
04/11/2019
8
1. The Contract Notice (ref 2019/S 182-442060) at Section II 1.4 states that “The purpose of this assignment [...]
As indicated in the Contract Notice, projects in South Africa are not eligible under this programme.
04/11/2019
51
Accelerated access to increased levels of finance sources is often dependent on the country credit rating [...]
It is up to the consultant to propose in its methodology the selection criteria it considers the most [...]
04/11/2019
12
According to p. 13 of the ToR: "Special surveys such as topographic, geological, geotechnical, environmental [...]
The contracting Authority confirms that all costs for special surveys are to be included in the Global [...]
04/11/2019
62
All facilities and support must be included in the price. Does this mean included in the fee?
All expenses other than those defined as eligible incidental expenditure and expenditure verification [...]
04/11/2019
22
Can EIB confirm that the General Conditions of Contract that are part of this tender are identical to [...]
The General Conditions included in the tender dossier are those that will apply to this Service Contract [...]
04/11/2019
44
Can we assume that (selected) project will not be situated in high risk countries and/or regions? If [...]
Projects should be selected in locations and countries where the likelihood for successful preparation [...]
04/11/2019
66
Can we assume that the level of ESIA is related to the level of detail of the project?
The contracting Authority confirms that the level of ESIA is related to the level of detail of the projects [...]
04/11/2019
48
Can you confirm that only one original Technical offer and Financial offer have to be submitted?
The Technical offers and the financial offers must be submitted in separate envelopes (double envelope [...]
04/11/2019
45
Can you confirm that the fields in which (at least 20 of) the permanent staff of the tenderer are required [...]
The Contracting Authority confirms that the permanent staff of the tenderer are required to work are: [...]
04/11/2019
54
Can you indicate the maximum number of references to be provided?
The maximum number of references to be provided is 15.
04/11/2019
6
Can you please confirm that the reference period for technical capacity of tenderer (ITT 5.3 a) and 5.3 [...]
It is 5 years.
04/11/2019
49
Can you please indicate what you do consider as “The electronic version of the technical offer” that [...]
The Technical offers and the financial offers must be submitted in separate envelopes (double envelope [...]
04/11/2019
50
Can you please indicate whether an electronic version of the financial offer must be included with the [...]
The Technical offers and the financial offers must be submitted in separate envelopes (double envelope [...]
04/11/2019
46
Can you please specify the reference period (since reference is made to ‘the last three years from submission [...]
The Contracting Authority confirms that the reference period for the project presented as references [...]
04/11/2019
30
Could you please clarify if South Africa is included in the project? The contract notice excludes South [...]
Yes, the Contracting Authority confirms that South Africa is excluded from the scope of this programme [...]
04/11/2019
55
Could you please confirm that the maximum budget available for this contract, as stated in the contract [...]
The maximum budget available refers to the grand total (A+B+C) as specified in the Section C, Annex 4 [...]
04/11/2019
13
Could you please confirm the deadline to submit our technical and Financial offers ? Is it the 12 or [...]
The deadline for submitting the offers is the 15th of November 2019, 23:59 CET. A corrigendum will be [...]
04/11/2019
39
CVs for non-key experts are not requested and will not be evaluated. How do you expect the Tenderer to [...]
Information pertaining to the access to non-key experts will be evaluated as part of the Organisation [...]
04/11/2019
26
For purpose of tax calculation, kindly provide us with information on: 1 the time expressed in months [...]
Please refer to the preceding answers.Question25
04/11/2019
59
Given the complexity of the assignment we herewith kindly request an extension of the submission of the [...]
The deadline for submitting the offers is the 15th of November 2019, 23:59 CET. A corrigendum will be [...]
04/11/2019
65
How much exposure is desired by the EIB?
It is up to the consultant to propose actions of visibility as defined in the Terms of Reference.
04/11/2019
14
In regard to the Technical capacity of the tenderer (Selection criteria 5.3), could you please confirm [...]
The Contracting Authority confirms that the reference period for the project presented as references [...]
04/11/2019
1
In section C - Annex 1 there are two formats of the tender submission form. Can you please inform if [...]
There is one submission form where you have to provide financial and professional data and references [...]
04/11/2019