25
|
We notice that there is a standard formulation that the project is free of taxes. It is our experience [...]
|
The Consultant might be exempt from direct and indirect taxes in the countries where it will have to [...]
|
04/11/2019
|
|
7
|
1) In the ITT, ‘3. Technical capacity of the tenderer’ the selection criteria mentions a reference period [...]
|
The reference period for the projects is 5 years. One original hardcopy and an electronic version should [...]
|
04/11/2019
|
|
8
|
1. The Contract Notice (ref 2019/S 182-442060) at Section II 1.4 states that “The purpose of this assignment [...]
|
As indicated in the Contract Notice, projects in South Africa are not eligible under this programme.
|
04/11/2019
|
|
51
|
Accelerated access to increased levels of finance sources is often dependent on the country credit rating [...]
|
It is up to the consultant to propose in its methodology the selection criteria it considers the most [...]
|
04/11/2019
|
|
12
|
According to p. 13 of the ToR: "Special surveys such as topographic, geological, geotechnical, environmental [...]
|
The contracting Authority confirms that all costs for special surveys are to be included in the Global [...]
|
04/11/2019
|
|
62
|
All facilities and support must be included in the price. Does this mean included in the fee?
|
All expenses other than those defined as eligible incidental expenditure and expenditure verification [...]
|
04/11/2019
|
|
22
|
Can EIB confirm that the General Conditions of Contract that are part of this tender are identical to [...]
|
The General Conditions included in the tender dossier are those that will apply to this Service Contract [...]
|
04/11/2019
|
|
44
|
Can we assume that (selected) project will not be situated in high risk countries and/or regions? If [...]
|
Projects should be selected in locations and countries where the likelihood for successful preparation [...]
|
04/11/2019
|
|
66
|
Can we assume that the level of ESIA is related to the level of detail of the project?
|
The contracting Authority confirms that the level of ESIA is related to the level of detail of the projects [...]
|
04/11/2019
|
|
48
|
Can you confirm that only one original Technical offer and Financial offer have to be submitted?
|
The Technical offers and the financial offers must be submitted in separate envelopes (double envelope [...]
|
04/11/2019
|
|
45
|
Can you confirm that the fields in which (at least 20 of) the permanent staff of the tenderer are required [...]
|
The Contracting Authority confirms that the permanent staff of the tenderer are required to work are: [...]
|
04/11/2019
|
|
54
|
Can you indicate the maximum number of references to be provided?
|
The maximum number of references to be provided is 15.
|
04/11/2019
|
|
6
|
Can you please confirm that the reference period for technical capacity of tenderer (ITT 5.3 a) and 5.3 [...]
|
It is 5 years.
|
04/11/2019
|
|
49
|
Can you please indicate what you do consider as “The electronic version of the technical offer” that [...]
|
The Technical offers and the financial offers must be submitted in separate envelopes (double envelope [...]
|
04/11/2019
|
|
50
|
Can you please indicate whether an electronic version of the financial offer must be included with the [...]
|
The Technical offers and the financial offers must be submitted in separate envelopes (double envelope [...]
|
04/11/2019
|
|
46
|
Can you please specify the reference period (since reference is made to ‘the last three years from submission [...]
|
The Contracting Authority confirms that the reference period for the project presented as references [...]
|
04/11/2019
|
|
30
|
Could you please clarify if South Africa is included in the project? The contract notice excludes South [...]
|
Yes, the Contracting Authority confirms that South Africa is excluded from the scope of this programme [...]
|
04/11/2019
|
|
55
|
Could you please confirm that the maximum budget available for this contract, as stated in the contract [...]
|
The maximum budget available refers to the grand total (A+B+C) as specified in the Section C, Annex 4 [...]
|
04/11/2019
|
|
13
|
Could you please confirm the deadline to submit our technical and Financial offers ? Is it the 12 or [...]
|
The deadline for submitting the offers is the 15th of November 2019, 23:59 CET. A corrigendum will be [...]
|
04/11/2019
|
|
39
|
CVs for non-key experts are not requested and will not be evaluated. How do you expect the Tenderer to [...]
|
Information pertaining to the access to non-key experts will be evaluated as part of the Organisation [...]
|
04/11/2019
|
|
26
|
For purpose of tax calculation, kindly provide us with information on: 1 the time expressed in months [...]
|
Please refer to the preceding answers.Question25
|
04/11/2019
|
|
59
|
Given the complexity of the assignment we herewith kindly request an extension of the submission of the [...]
|
The deadline for submitting the offers is the 15th of November 2019, 23:59 CET. A corrigendum will be [...]
|
04/11/2019
|
|
65
|
How much exposure is desired by the EIB?
|
It is up to the consultant to propose actions of visibility as defined in the Terms of Reference.
|
04/11/2019
|
|
14
|
In regard to the Technical capacity of the tenderer (Selection criteria 5.3), could you please confirm [...]
|
The Contracting Authority confirms that the reference period for the project presented as references [...]
|
04/11/2019
|
|
1
|
In section C - Annex 1 there are two formats of the tender submission form. Can you please inform if [...]
|
There is one submission form where you have to provide financial and professional data and references [...]
|
04/11/2019
|
|