20
|
In regards to section 1 and 3 of the document "2-3-0 - Technical Selection Questionnaire", it is indicated [...]
|
Only one Technical Selection Questionnaire shall be filled in per Tenderer. Thus, the requested information [...]
|
12/08/2014
|
|
19
|
In the invitation to tender, there is not packaging schema instruction included except the one referred [...]
|
The necessary "packaging instructions" are contained in document 6-0-0 – Guidebook for Tenderers (please [...]
|
12/08/2014
|
|
18
|
1.Could you please indicate if a Power of Attorney needs to be include in the answer to section 2-1-0 [...]
|
The Power of Attorney is included as Annex III of the Draft framework contract (document 7-0-0). However [...]
|
12/08/2014
|
|
17
|
On page 181 of the numbered specifications, the second table requires detailing the average number of [...]
|
Your understanding is correct.
|
06/08/2014
|
|
16
|
Are Annexes (except the ones already required/defined in the Questions to be answered) to the core documents [...]
|
Yes; please refer to §1 "Introduction" of document 2-4-0 "Technical Evaluation – Questionnaire".
|
06/08/2014
|
|
15
|
a) There seem to be some inconsistencies between the timeframes defined for the various steps of the [...]
|
a) In case of inconsistencies between the ITSS-T&M-III Roadmap (§4.2, schematic overview, p.19) and [...]
|
06/08/2014
|
|
14
|
Regarding the CV template provided (2-3-2 Technical Selection – CV Form), could you please clarify the [...]
|
1. One purpose of the stage of Technical Selection is to assess the tenderer’s technical capacity to [...]
|
06/08/2014
|
|
13
|
The specifications state that a consultant having more than 10 years of experience in the domain (DE) [...]
|
Your understanding is correct. The level of specific competence defines a minimum number of years (document [...]
|
06/08/2014
|
|
12
|
It seems that the draft contract provided with the CFT is in fact a very wide template that has not yet [...]
|
The draft framework contract provided as Annex 7-0-0 of the Tendering specifications is indeed a template [...]
|
30/07/2014
|
|
11
|
We understand that the measurement of ratio SC/R will begin at contract start and weekly. We also understand [...]
|
1. The SC/R ratio is applied for each specific profile. Levels are not any more considered. 2. The ratio [...]
|
30/07/2014
|
|